Whether related network adaption lines are already laid out
3.3 Installing the RG-S3250E Series
3.3.1 Precautions
During installation, note the following points:
Connect the power cables of different colors to the corresponding grounding posts.
Ensure that the connected power cables have sound contact.
Do not place heavy items on the switch.
Reserve a spacing of at least 10 cm around the chassis for good ventilation. Do not stack the devices.
The switch should be located at places free from the large power radio launch pad, radar launch pad, and
high-frequency large-current devices. If necessary, electromagnetic shielding should be adopted. For
example, use interface cables to shield cables.
Interface cables should be laid inside the equipment room. Outdoor cabling is prohibited, avoiding damages
to device signal interfaces caused by over-voltage or over-current of lightning.
3.3.2 Mounting the Switch to a Standard 19-inch Rack
The RG-S3250E series switches follow the EIA standard dimensions and can be installed in 19-inch distribution
cabinets. During the installation, place the front panel of the switch to the rack. For safety purposes, screw up the
randomly distributed screws as shown in the following figure.
3.3.3 Mounting the Switch to the Wall
The supplemented hangers of the RG-S3250E series support the installation on walls, as shown in the following