Installation
EVWM-V01-R1 Installation and Operation Manual
WallPod Intelligent EV Charging Unit
December 2022
Page
22
of
35
IMPORTANT:
It is the responsibility of the installing engineer to satisfy themselves, that all accessible
cable terminations throughout this product are secure and have not become loose,
strained, or disconnected during transit and/or installation.
11. Switch ON the power to the chargepoint and test in accordance with the current
legislation applicable in the geographical region of the installation.
12. Make sure you are satisfied that the electrical installation is complete then, if
required, temporarily close the chargepoint enclosure for safety and security.
Access to the components will be needed during the configuration process.
Install Load Balancing
NOTE
: This manual assumes the installation of a single chargepoint. Whilst multiple
chargepoints can be connected in a similar way, installers may wish to consider
connecting/monitoring via third-party equipment.
If connecting/monitoring via third-party equipment, make sure you are fully aware of
the manufacturer’s instructions so that the device/system can be installed correctly and
in conjunction with the chargepoint installation.
If load balancing will be enabled on this chargepoint it should, ideally, be installed
alongside the ‘standard installation’.
If installing at a later date, work may be required to enable entry of the CT cable into the
chargepoint enclosure.
Overview
Power coming into the property is monitored by a Current Transformer (CT) that clamps
around the property’s incoming power cable and is then connected to the chargepoint.
x
The CT has a cable allowing it to be connected to the chargepoint.
x
Additional cable may be added to the CT cable but to maintain a good signal, it is
recommended that cables extensions are kept as short as possible.
Connect the CT to the Property
1. The CT clamp should be positioned around the
Live
(positive) cable between the
Meter and the Consumer Unit.
2. The arrow shown on the CT clamp must point in the direction of electrical flow
TOWARD the consumer unit.
x
Alternatively, if required, the CT clamp may be positioned on the Negative
cable leaving the Consumer Unit. The arrow on the CT clamp must point in
the direction of electrical flow AWAY from the consumer unit.
3. Release the clip on the CT clamp then open the clamp.
4. Place the CT clamp around the power cable.
x
Make sure the arrow on the clamp points in the correct direction.
x
No other cables should pass though the CT clamp.
5. Close the CT clamp and secure it with the clip.