46
CHAPTER 12
INSULATION RESISTANCE MEASUREMENT FOR
VARIOUS EQUIPMENTS
Insulation resistance is measured while manufacturing various equipments like
transformer, circuit breakers, cables etc. It should be noted that the negative measurement
lead should not be connected to large ground conductors. Following are the connections
schemes for insulation resistance measurement for different equipments:
12.1 TRANSFORMERS:
HV winding (with 3 phases
short) to LV winding (with
3 phases short)
HV winding (with 3 phases
short) to ground with LV
winding guarded
LV winding (with 3
phases short) to ground
with HV winding guarded
HV winding (with 3 phases short)
to LV winding (with 3 phases
Positive terminal of insulation
tester
Negative terminal of insulation
tester
G
Guard terminal of insulation
tester