Installation & Servicing Instructions Rinnai Q Premier
10
!
CAUTION
4.2 Transportation
The boiler may be damaged when not secured properly.
- Only transport the boiler using appropriate transportation equipment, such as a
handtruck with a fastening belt or special equipment for maneuvering steps.
- When shipping the boiler must be secured on the transportation equipment to
prevent it from falling off.
- Protect all parts against impacts if they are to be transported.
- Follow the transportation markings on the packaging.
•
Packaged boilers must always be lifted and carried by two people, or you must
use a handtruck or special equipment for transport.
The boiler is delivered on a pallet in a card board box. After removing the packaging
certain parts of the casing can be removed to reduce weight for indoor transportation
as follows (see
fi
gure 1):
1. Open the smoke glass door;
2. Remove the 2 screws just below the upper edge;
3. Lift the front top part at the front;
4. Close the smoke glass door and pull the complete front panel at the top towards
you;
grips
fi gure 2
1
3
4
removing
boiler
casing
fi gure 1
2
!
CAUTION
!
WARNING
!
CAUTION
Store all removed parts after transportation and during
installation in a safe place.
Lift the boiler only by the boiler's grips and the rear
wall. See fi gure 2. Use protective gloves.
When tilting the boiler, testing water may drain from
the boiler.
Reassembly of the components is done in reverse order.
Make sure the pins are positioned correctly in the
snap locks.