User Instructions
8.1 Commissioning and hand over
WARNING
As part of the commissioning programme, the commissioning engineer must go through the following with the
operator.
(i) Lighting, shutdown, and operational information.
(ii) Safety features, data plate, and labelling.
(iii) The requirement for regular inspection - especially if the heater is within a more demanding environment - and the need for regular
servicing, carried out by competent and qualified engineers.
CAUTION
After approximately 100 hours of running, the fan must be checked to ensure that it is correctly working. It is
strongly advised that this is undertaken by the commissioning engineer, and not the operator
8.2 Servicing
WARNING
Servicing must be carried out on a regular basis, the maximum interval between services being one year.
It is a requirement that only suitably qualified and competent persons are allowed to undertake the servicing.
The manufacturers advise that the planned service schedule as detailed in section 4.1 of the Installation,
Commissioning and Servicing Manual is adopted by the user.
Further details are available from either the commissioning engineer or from the Manufacturer (details below).
8.3 Start Up Procedure
(a) Enable burner via controller by selecting ‘Heat’ (Relay 2); ‘Heat On’; ‘Heat/Auto’.*
(* dependent on control type supplied. Refer to individual controller operating manual.)
(b) Burner will fire and establish within 60seconds.
(c) As temperature of heater increases, fan will operate.