Install Front Roofing — Not Supplied in Kit
1.
Install metal roof edging along the end walls and
the front edge of the roof sheathing.
2.
Install shingles according to the instructions on the wrapper.
If you need more detailed instructions on installing shingles,
there are good publications at book stores or newsstands.
Roof Sheathing
1x6
Trim
Metal Roof Edge
2x4 Overhang
Supplement Details
Header Support
1.
If you purchased a 32"x80" entry door, locate where you want the opening to be and build a
37-1/2" door header. You'll need to cut (4) four 37-1/2" long 2x4s, (3) three 5-5/8" long 2x4s
and a 3-1/2"x37-1/2" piece of OSB. If you have a different size door adjust accordingly.
2.
Assemble header as shown in Detail 'A'. First assemble (2) two 37-1/2" 2x4s and OSB. Next
assemble (1) one 37-1/2" 2x4 and (3) three 5-5/8" 2x4s. Nail this assembly to bottom of previous
assembled pieces. Last nail the remaining 2x4 to the 5-5/8" boards. Use 10d sinkers for all.
3.
Secure the header by nailing through the top plate and wall studs with 10d sinkers.
4.
Cut (2) two header supports from pre-cut wall studs and install under the door header.
Detail 'A'
(2) two 2x4s on edge with
OSB nailed in between.
2x4 flat
5-5/8" 2x4s
This assumes a 92-5/8" long stud length. Adjust accordingly if stud length differs