Insert (2) two plyclips into the roof sheathing
between each truss at the top row.
3.
Apply roof sheathing across the top of the roof. There will be an air space at the
peak of the trusses to allow for ventilation.
Straight Edge
To prevent the nails from protruding
thought the bottom of the soffit board,
do not nail at an angle when nailing roof
sheathing to the soffit boards.
28-1/2” x 48”
Plyclip
42” x 48”
42” x 72”
42” x 76-1/2”
13” x 72”
Install This Row First
13” x 48”
48” x 72”
48” x 72”
13” x 76-1/2”
42” x 48”
48” x 72”
13” x 48”
1.
Install a 42" x 72" OSB roof panel flush with
the face of the rear gable trim. Use a straight
edge to align the top of the sheathing with the
top of the truss. Continue adding sheathing
following the layout below. Use 6d common
nails, spaced 12" apart.
2.
Repeat step for opposite side.
Step 15
Install Roof Sheathing