Step 8B
Build Center Wall Brace & Set Walls
Center Wall Brace
DETAIL 'D'
Step 9
Install 1x4 Trim
1x4 Trim
flush
1.
Install (2) two 84-1/2" long 1x4 corner trim on the back wall, flush with the siding on the
sidewall and the top 2x4 wall plate. Use 6d galv. nails.
2.
Install (2) two 1x4-72" trim boards across the top of the back wall. Cut to fit. Install the 1x4
boards flush with the top of the 2x4 top plate. See diagram below.
3.
Repeat steps for front wall trim.
Back and Front Walls
1x4 72" Top Trim
Cut to Fit
1x4 84-1/2" Corner Trim
Sidewall
12. Install the center Wall Brace in the center of the building between the side walls. Make
sure the side walls are plumb. The shorter 2x4s will butt against a wall stud. Secure the
longer 2x4 to the side of the stud with (2) two 3" long wood screws.