- 1 -
INSTALLATION INATRUCTIONS
PREPARATION FOR INSTALLATION:
■
Feed water cannot be hot. It damages the RO membrane.
■
The perfect range of feed water pressure is between 5-25 psi.
If the feed water pressure is higher than 3.0Kg/cm
2
/40 psi, install the reduced pressure valve or take
off the booster pump. Otherwise the high water pressure may reduce in the leakage or break down.
If the feed water pressure is lower than 0-0.3Kg/ cm
2
/0-5psi, you have to wider the tube or shorten
the length of the pipe to the help the pump run normally. Otherwise, it may result in the reduction of
the production rate & percent rejection, the pump to deliver water.
■
Avoiding to install the purifier at the place where is damp, low temperature (<4
℃
) of the system or
high temperature (>40
℃
)
■
The storage tank can be place on its side without affecting the performance of the system. If there is
insufficient room under the sink, the tank may be located in an adjacent cupboard.
INSTALLATION OF WATER SUUPLY CONNECTION:
A. Water Supply Connector 1/2” FIP (L:36m/m)
(FWC-0808)
B. Deliver-
Ball Valve 1/4”MIP x1/4”OD1/4”
(BV-0404)
Assemble the water supply connector by inserting the Deliver-ball valve. Screw the deliver-ball valve
into the side of the water supply connector using 3 to 4 wraps of Teflon tape.
Disconnect the water supply line from the feed
water faucet underneath sink. Attach and tighten
water supply connector assembly being careful not
to pinch or crimp any tubing or water supply line
while tightening.
FAUCET INSTALLATION
■
Using the 1/4
” drill bit, drill a 1/4” hole through the base metal. Operate
the drill slowly and carefully, especially when the drill is about to
penetrate the metal. If necessary use two drops of oil in the hole.
■
Repeat step 1. Using the 1/2
” drill bit. Mount the faucet in the hole and
using an adjustable wrench (or hand) to hold the faucet, tighten the
9/16
” nut.
*** If it is not available to drill a hole, you may use a faucet-bracket instead. ***