background image

Air Intake Filter

  The integrated air compressor, of the N2-Blast

® 

FPS-900-

RS, has an air intake pre-filter. It prevents particles from entering 

the compressor housing and damaging internal components. 

Replace this filter once per year or every 1000 hours, whichever 
comes first. To do so, remove the pre-compressor filter cap by 

twisting it clockwise. Remove the old element and use a clean 

dry cloth to clean the filter bowl before installing the new ele

-

ment.

Air Filter Replacement

 

The particulate and coalescing filters, after the air compres

-

sor, are designed to capture particulate

and moisture prior to entering the rest of the system. These fil

-

ters need to be replaced once per year or every 1000 hours, 

whichever comes first. 

Note: Annual Filter replacement kit part # FRP-007

Follow these instructions to replace filters:

1.  Turn off the unit and remove the front cabinet door.
2. 

Locate the air filters on the bracket in the top-left of the 

cabinet (see Figure 10).

3. 

Make sure the filters are completely depressurized by 

checking the pressure gauge.

4. 

Remove  both  filter  bowls  by  turning  them  counter-

clockwise.

5. 

After removing the filter bowls, rinse debris out of the 

bowls with warm water.

6.  Dry the bowls with a clean dry cloth and replace old 

O-rings with the ones in the kits and lubricate the seals.

7. 

Change the filter elements:

a. Particulate Element - Pull the plastic element hous-

ing out of the filter bowl. Twist off the black plastic cover 

and pull off the particulate element. Install the new ele-
ment in the reverse order.
b. Coalescing Element - Twist the coalescing element 
counter-clockwise. Install the new element in the re-
verse order.

8.  After replacing all elements and O-rings and cleaning 

the bowls, install the bowls back to their corresponding 

filter housings. Hand-tighten only.

After replacing the filters, check the filter bowls for leaks by turn

-

ing on the unit momentarily. Turn the unit off to reinstall the front 
cover and then power the unit back on. Once powered up, the 
air compressor will turn on and the system will start producing 
nitrogen.

Key Contacts

 

Contact your local provider/installer for any questions about 

the performance and/or maintenance of the system. They will be 

best suited to answer your questions and your quickest solution 

on any issues you may have.  If they cannot be reached, contact 

the manufacturer at:

South-Tek Systems, LLC.

tel (888) 526-6284 fax (910) 332-4178

Email: [email protected]

FAQS

1.  Power Issues

If the N2-Blast

®

 FPS-900-RS does not have power, the produc-

tion and storage of nitrogen will become apparent once the stor-
age pressure drops.
•  Check the power cord.
•  Has the building’s circuit breaker or GFCI tripped? Locate 

the breaker and reset. If breaker continues to trip, you may 
have that circuit overloaded.

2.  Pressure Issues

The N2-Blast

®

 FPS-900-RS will produce and store Nitrogen (N

2

at 70 (+/-3) psig. Once the storage tank reaches 70 (+/-3) psig, 
the system will go into Standby Mode. When the pressure drops 
by about 7-10 psig, the system will go into Run Mode and begin 

to refill the storage tank. Contact the manufacturer or factory 

trained technician if system does not properly operate within 
these ranges

Nitrogen Pressure Check:

 

The pressure gauge on the storage tank should be between 

60 and 70 psig. If the pressure is low, check the following:

•   Check the power.

•   Find out if fire protection system is being tested.

•   Check for leaks throughout system.

3. Leaks

As with any gas system, only use a spray bottle on non-electri-

cal equipment to find leaks. Fix or replace leaking fittings or old 
hose. Push-to-connect fittings will show bubbles and typically 

have up to a 5ccm acceptable leakage rate. Contact your local 
provider/installer for help.

12.

Содержание N2-Blast DDX-LP PrePaK

Страница 1: ...rePaK system incor porates a South Tek Systems FPS 900 pressure swing adsorp tion N2 Blast nitrogen generator complete with independent air compressor nitrogen storage tank and control system The nitr...

Страница 2: ...ar The 2 2 1 2 3 and 8 sizes are rated for a maximum pressure of 250 psi 17 2 bar and the 4 and 6 sizes are rated for a maximum pressure of 300 psi 20 7 bar Water temperature must be maintained betwee...

Страница 3: ...3 Fig 1...

Страница 4: ...nal box mounted on the inside of the enclosure All field wiring connec tions are made at this terminal box A separate power connection is provided for the optional air compressor Note The air compress...

Страница 5: ...16 Secure the handle of the Model B Manual Emergency Station in the OFF position with a nylon tie supplied with the assembly Inspection And Testing Of The DDX LP PrePaK Systems Refer to Figure 2 1 Wat...

Страница 6: ...6 Fig 2 Model DDX LP Low Pressure Dry Pipe System Valve Legend Note Some items omitted for clarity...

Страница 7: ...7 Fig 3...

Страница 8: ...er has drained then close Note Leaving the condensate drain open for an extended pe riod of time may allow excess air nitrogen to bleed off and result in accidental release of the Model LP Dry Pilot A...

Страница 9: ...r can lead to incorrect gas supply The nitrogen generator produces nitrogen at a low flow rate which quickly dissipates into the air Nitrogen is not poison ous but do not directly inhaled since high c...

Страница 10: ...not adjust the factory preset cut in and out pressure without first consulting with South Tek Systems Patented BlastOff Leak Detection System The BlastOff Leak Detection is a patented feature which se...

Страница 11: ...r further troubleshoot ing Low System Pressure Alarm Mode Lo n2 The low system pressure alarm activates when a sys tem pressure is detected below the normal functioning limits of the nitrogen generato...

Страница 12: ...esponding filter housings Hand tighten only After replacing the filters check the filter bowls for leaks by turn ing on the unit momentarily Turn the unit off to reinstall the front cover and then pow...

Страница 13: ...Fig 5 Nitrogen Generator Filter Locations 13...

Страница 14: ...o 580 gallons 9 Nitrogen Generator Model B1 Accelerator 3 3 2 1 HP 115 VAC Systems up to 1170 gallons 4 4 3 1 2 HP 220 VAC 60 Hz Systems up to 580 gallons A 2 w System Side Control Valve 4 1 HP 220 VA...

Отзывы: