COMMISSIONING INSTRUCTIONS

BEFORE FILLING, CHECK EXPANSION VESSEL CHARGE IS AT 3.0 BAR.

1. Open all terminal fittings on the domestic hot water circuit. Open the main supply to the unit.

2. Flush through until all air is expelled.

3. Close hot outlets and open all cold outlets connected to the tee after the pressure control valve.

4. Flush through until all air is expelled.

5. The system is now full of water.  Check for any leaks on pipework or joints or components such

as immersion heaters etc. It is the responsibility of the installer to check all fittings, including
those that are fitted to the unit.

6. Switch on power and heat up via immersion heater, and/or boiler.

7. Your system should be ready for use.

MAINTENANCE

Maintain annually and carry out the following checks:

Clearly up date the Benchmark Log Book at each service -

GUARANTEES ARE VOID WITHOUT SERVICE RECORDS.

1. Check incoming pressure is controlled at 3 bar maximum. The gauge reading clearly demonstrates this.

Expansion vessels must be maintained annually. The charge should be checked with an accurate
pressure gauge and maintained at 3.0 bar. If the reading is less than 3.0 bar to recharge the vessel
ensure that the unit is decommissioned by turning off the water supply and opening hot tap. Open
the pressure and temperature relief valve to drain water from the top of the unit then close this valve.
Leaving the hot tap open and the main supply off, pump the vessel using a schraeder valve connector
via a footpump or motorised pump to 3.0 bar. Remove pump, open mains supply and close hot tap
once water is running freely.

Run a hot tap and close. If the pressure remains over 3 bar, re-calibrate the Pressure Reducing Valve
and clean the strainer, replacing if necessary.

2. Open the expansion valve cap to manually discharge water to ensure that it works, making sure that

it resets correctly.

3. Open the pressure and temperature relief valve cap to manually discharge water to ensure that it works,

making sure that it resets correctly.

4. In both cases ensure that discharge pipework is adequate to safely carry discharged water away. 

If not, check for blockages etc. and clear.

5. Check that the controls of the hot water temperature do not allow the water to get hotter than 60ºc.

New Stainless imp_alt  2/15/05  12:15 PM  Page 12

Содержание LWSS STAINLESS STEEL

Страница 1: ...R LWSS STAINLESS STEEL UNVENTED WATER STORAGE HEATER APPLIED ENERGY PRODUCTS LTD TEL 08709 000430 THIS UNIT IS SUPPLIED BY INSTALLATION COMMISSIONING MAINTENANCE...

Страница 2: ...re will result in a fall in flow rate A flow rate of 20 litres per minute is a minimum requirement for single bath applications and must rise proportionately for greater demands 1 PRESSURE AND TEMPERA...

Страница 3: ...RESSURE GAUGE EXPANSION VESSEL OPTIONAL DRAIN POINT EXPANSION VALVE COLD TAPS COLD FEED 22mm EXPANSION VALVE 22mm TUNDISH 15mm 15mm PRESSURE AND TEMPERATURE RELIEF VALVE 2 DISCHARGE Both the pressure...

Страница 4: ...ween 9m and 18m equivalent resistance length should be at least larger than the nominal outlet size of the safety device between 18m and 27m at least 3 sizes larger and so on Bends must taken into acc...

Страница 5: ...systems so that any installation can be traced reasonably easily The single common discharge pipe should be at least one pipe size larger than the largest individual discharge pipe to be connected If...

Страница 6: ...up to 9m up to 18m up to 27m up to 9m up to 18m up to 27m 22mm 28mm 35mm 28mm 35mm 42mm 35mm 42mm 54mm 15mm 22mm 28mm G1 2 G3 4 G1 0 8m 1 0m 1 4m 1 0m 1 4m 1 7m 1 4m 1 7m 2 3m GUIDANCE NOTES TYPICAL D...

Страница 7: ...y HOT WATER OUTLETS Dynamic pressure always drops across a system when more than one outlet is opened The unit has a working pressure of 3 bar Good system design should take this into consideration pi...

Страница 8: ...with a 3mm contact gap separation Appropriate wiring for the electrical load must be used The twin immersion heaters supplied with direct units can be switched to utilise low tariff electricity supply...

Страница 9: ...75 or CP15 Programmer L C 2 C 2 1 Power Supply E Junction Box N L G Y BR BL 2 4 1 ITD Dual Stat ITD Dual Stat The wiring diagram for Danfoss systems is given as guidance For modified Danfoss Randall Y...

Страница 10: ...rammers recommended are FP715 7 5 and 2 day programming and the CP15 5 2 and 24 hour programming S PLAN Zone Valve Htg Room Stat Zone Valve DHW HP22 1 2 2 8 9 10 7 6 5 4 3 2 1 1 2 3 2 3 3 2 2 1 RMT 23...

Страница 11: ...e FP715 7 5 and 2 day programming and the CP15 5 2 and 24 hour programming 8 9 10 7 6 5 4 3 2 1 2 1 2 3 3 3 2 2 1 L N E L N E Htg On Dhw On Dhw Off L L N 4 3 1 NOT USED N E Basic Boiler 2 Port Valve P...

Страница 12: ...he charge should be checked with an accurate pressure gauge and maintained at 3 0 bar If the reading is less than 3 0 bar to recharge the vessel ensure that the unit is decommissioned by turning off t...

Страница 13: ...RE SET TEMPERATURE HIGH LIMIT CUT OUT C TEMPERATURE AND PRESSURE RELIEF VALVE D EXPANSION RELIEF VALVE E PRESSURE REDUCING VALVE LINE STRAINER F EXPANSION VESSEL SUPPLIED LOOSE G NON RETURN VALVE H PR...

Страница 14: ...WITH MANUAL RE SET TEMPERATURE HIGH LIMIT CUT OUT C TEMPERATURE AND PRESSURE RELIEF VALVE D EXPANSION RELIEF VALVE E PRESSURE REDUCING VALVE LINE STRAINER F EXPANSION VESSEL SUPPLIED LOOSE G NON RETUR...

Страница 15: ...IMMERSION HIGH LIMIT THERMOSAT IMMERSION CONTROL THERMOSTAT EXPANSION VESSEL UP TO 170 LITRE MODELS EXPANSION VESSEL FOR 200 250 LITRE MODELS TUNDISH INSTALLATION GUIDE LABEL CYLINDER THERMOSTAT 2 PO...

Страница 16: ...priately approved competent personnel following relevant Code of Practice 5 Installation must be in an appropriate location and use is restricted to potable water Please note that the extended guarant...

Страница 17: ...H LIMIT CUT OUT IS ALL WIRING TO THE CONTROLS OK YES NO NO NO NO YES RE SET YES REPLACE THERMOSTAT RE WIRE IS CONTROL TEMPERATURE SET AT 55 o C 60o C YES NO RE SET SET PROGRAMME IS BOILER ON START YES...

Страница 18: ...G NO HOT WATER DIRECT IS POWER ON TO ELEMENTS IS CONTROL TEMPERATURE SET AT 55 o C 60o C START END YES HAS HIGH LIMIT TRIPPED YES NO NO NO YES CHECK WIRING LINKS CONTINUITY AND RE SET REPLACE ELEMENT...

Страница 19: ...URE ADEQUATE IS IN LINE STRAINER IN PRV DIRTY START END YES IS PRV FAULTY IS SYSTEM FREE FROM RESTRICTIONS BLOCKAGES NO YES YES NO YES NO NO WATER SERVICE CHECK BY SUPPLYCOMPANY REQUIRED CLEAN OR REPL...

Страница 20: ...o C IS EXPANSION VESSEL CHARGE CORRECT IS ERV TPRV DISCHARGING REPLACE ERV TPRV RESET TEMPERATURE END CLEAN OR REPLACE AS REQUIRED RECOMMISSION EXPANSION LEVEL RE CALIBRATE PRV IS VALVE SEAL AND SEAT...

Страница 21: ...CE 2 DATE ENGINEER NAME COMPANY NAME TEL No ID SERIAL No COMMENTS SIGNATURE SERVICE 3 DATE ENGINEER NAME COMPANY NAME TEL No ID SERIAL No COMMENTS SIGNATURE SERVICE 4 DATE ENGINEER NAME COMPANY NAME T...

Страница 22: ...PRESSURE BAR HAS STRAINER IF FITTED BEEN CLEANED OF INSTALLATION DEBRIS YES NO HAS A WATER TREATMENT DEVICE BEEN FITTED YES NO IF YES TO ABOVE THEN WHAT TYPE ALL MAINS PRESSURE SYSTEMS ARE T P AND EX...

Страница 23: ...etc CUSTOMER DETAILS NAME ADDRESS TEL No INSTALLER DETAILS NAME DATE ADDRESS TEL NO REGISTRATION DETAILS Where applicable for unvented systems etc REG No ID SERIAL No etc COMMISSIONING ENGINEER DETAI...

Страница 24: ...ustomer APPLIANCE DETAILS COMMISSIONING RECORDS SERVICE INTERVAL RECORD IMPORTANT FAILURE TO INSTALL COMMISSION THIS APPLIANCE TO THE MANUFACTURER S INSTRUCTIONS MAY INVALIDATE THE WARRANTY This note...

Отзывы: