DOUBLE DOOR END
If you have purchased a double door for your greenhouse the procedure for construction of the gable is identical to the single
door model. There are, however, a small number of differences outlined as follows:
There are only 2 packs of aluminium
- double door corner bars
- Double door end
The door end contains the cill and main door track support (which are separate on the single door model).
The apex gusset plate has a 5
th
hole in to accommodate a short glazing bar above the door.
The horizontal and diagonal Angle braces are a little thicker and are made from unequal angle.
PROCEDURE:
1.
Follow the text and drawing on the previous pages as the construction is the same apart from some bars being shorter,
longer and thicker.
2.
Having fitted the main door track support in a similar way to the single one, you must not fit the short glazing bar that goes
above it at this stage. (Key point). This will be fitted later when the doors have been installed (see later text).
Do not fit the top door track at this stage.
You have now completed the main frames of the structure, which can now be joined together. You need not do this procedure
on the base but any flat surface near the Polycarbhouse site. If your base is prepared however, you can carry out the assembly
there to save lifting it on later. But before this we construct the vents and doors.
Содержание Statesman 2.43m x 3.65m
Страница 2: ...2 ...
Страница 3: ...3 IF SUPPLIED ...
Страница 9: ...9 G R GR GLAZING RUBBER GR GR GR GR GR GR NO Glazing Bead ...
Страница 18: ...18 ...
Страница 26: ...26 ...