6 Checking hardware installation
Raisecom Proprietary and Confidential
Copyright © Raisecom Technology Co., Ltd.
34
Table 6-2
Checklist of cabinet or workbench
Item
Requirement
Cabinet
Structure attachments are installed correctly and reliably, switches of
doors and locks work normally.
All other connection bolts are installed correctly and reliably, the flat
washers and spring washers are installed in a correct order.
The installation location meets the engineering design manual.
The installation is fixed and reliable and consistent with the anti-seismic
requirements described in the engineering design manual.
The ground cable is correctly connected.
The ESD wrist strap is connected to the ESD jack on the cabinet.
Workbench
The installation location meets the engineering design manual.
The installation is fixed and reliable and consistent with the anti-seismic
requirements described in the engineering design manual.
The ground cable is correctly connected.
The ESD wrist strap is connected to the ESD jack on the cabinet.
6.3 Checking chassis and cards
Check the chassis and card after installation according to Table 6-3.
Table 6-3
Checklist of chassis and card
Item
Requirement
Chassis
Placed firmly and there is enough space for heat dissipation and
operation around the device. The ground cable is connected
correctly.
Fill unoccupied slots with blank panels for dust prevention and
electromagnetic shielding.
Components
The installation slots of all components are correct.
Install all components firmly without slackening.
6.4 Checking cables
Check cables after installation according to Table 6-4.