background image

7

It is strongly recommended that only metal pipe-

work should be used. No responsibility will be 

taken for any damage caused from discharges.

The discharge pipe D2 should be at least one pipe 

size larger than the nominal outlet size of the 

safety device unless its total equivalent 

hydraulic resistance exceeds that of a straight 

pipe 9m long, i.e. for discharge pipes between 9m 

and 18m the equivalent resistance length should 

be at least two sizes larger than the nominal 

outlet size of the safety device; between 18 and 

27m at least 3 sizes larger than the nominal outlet 

size of the safety device; between 18 and 27m at 

least 3 sizes larger, and so on; bends must be 

taken into account in calculating the flow 

resistance. See Figure 1, Table 2  and the worked 

example.

Note: An alternative approach for sizing 

discharge pipes would be to follow Annex D, 

section D.2 of BS 6700:2006 + A1:2009).

Trapped

gully

Fixed

grating

Discharge below

fixed grating 

tundish

Metal discharge pipe (D1) from

temperature relief valve to tundish

Metal discharge pipe (D2) from tundish,

with continuous fall. See Table and

worked example

300mm

minimum

600mm maximum

Safety device

(eg. temperature

relief valve)

Figure 1: Typical Discharge Arrangement

Valve Outlet 

Size      [-]

Minimum size of 

discharge pipe before 

tundish   [mm]

Minimum size of 

discharge pipe after 

tundish   [mm]

Maximum allowed length 

of pipe after tundish    [m]

Length to be subtracted 

for each elbow or bend   

[m]

22

9

0.8

28

18

1.0

35

27

1.4

28

9

1.0

35

18

1.4

42

27

1.7

35

9

1.4

42

18

1.7

54

27

2.3

15

22

28

G1/2 

G3/4

G1

Table 2: Sizing of copper discharge pipe “D2” 

for common temperature relief valve outlet sizes

Pre-Installation

This example is for a G½ temperature relief valve 

with a discharge pipe (D2) (as fitted on 125l to 

300l cylinders) having 4 No. 22mm elbows and 

length of 7m from the tundish to the point of dis-

charge.

From Table 2, the maximum resistance allowed for 

a straight length of 22mm copper discharge pipe 

(D2) from a G½ temperature relief valve is 9.0m. 

Subtract the resistance for 4 No. 22mm elbows at 

0.8m each = 3.2m.

Therefore the maximum permitted length equates 

to 5.8m, which is less than the actual length of 

7m, therefore calculate the next largest size.

Maximum resistance allowed for a straight length 

of 28mm copper discharge pipe (D2) from a G½ 

temperature relief valve equates to 18m.

Subtract the resistance for 4 No. 28m.m elbows at 

1.0m each = 4m. 

Therefore the maximum permitted length equates 

to 14m.

As the actual length is 7m, a 28mm (D2) copper 

pipe will be satisfactory.

•  Where a single common discharge pipe serves   

more than one system, it should be at least 

one pipe size larger than the largest individual 

discharge pipe (D2) to be connected.

•  The discharge pipe should not be connected to 

a soil discharge stack unless the soil discharge 

stack is capable of safely withstanding temper-

atures of the water discharged, in which case, 

it should:

      - contain a mechanical seal, which allows  

        

                water  into  the  branch  pipe  without  allowing                                                                                                                                

        foul air from the drain to be ventilated  

        through the tundish. 

      - there should be a separate branch pipe with 

        no sanitary appliances connected to it. 

      - if plastic pipes are used as branch pipes 

        carrying discharge from a safety device, 

        they should be either polybutalene (PB) or 

        cross-linked polyethylene (PE-X) complying 

        with national standards. 

      - be continuously marked with a warning that 

        no sanitary appliances should be connected 

        to the pipe.

5.4.2 

Worked Example

Содержание IOT Series

Страница 1: ...Quantum IOT Electric Cylinders Installation and User Instructions R04329 1 Installation and User Instructions Important This manual must be left with user after Installation...

Страница 2: ...rovided to the custom er for future reference Installers are required to carry out installation commissioning and ser vicing work in accordance with the Benchmark Code of Practice which is available f...

Страница 3: ...Pipe D2 10 6 3 3 Tundish 10 6 4 Immersion Heaters 10 6 5 Electrical Connection 10 6 6 Connection of Secondary Return 13 7 Commissioning 13 7 1 Verify Electronic Operation 14 7 2 Initialise System Set...

Страница 4: ...igh level cut out is fitted to the product for each heat source This should never activate under normal operation If an electronic copy of this manual should be required please contact the manufacture...

Страница 5: ...applied to prevent damage and dirt deposit inside the cylinder Pipework the pipe runs should be executed as short as possible unused pipework should be removed and all remaining pipework should be la...

Страница 6: ...he cylinder must come directly from the cold water mains after the mains stop valve to the property The cold water inlet pipework should have at least an inside diameter of 19mm and should meet the re...

Страница 7: ...ief valve outlet sizes Pre Installation This example is for a G temperature relief valve with a discharge pipe D2 as fitted on 125l to 300l cylinders having 4 No 22mm elbows and length of 7m from the...

Страница 8: ...lack HIPS ABS Inlet Outlet Pipe Stainless Steel Coils Corrugated Stainless Steel Insulation 60mm PU Foam GWP 1 ODP 0 T P Valve Brass LDPE Immersion Heater Incoloy and brass Tundish LDPE 6 Installation...

Страница 9: ...to a tundish and the discharge pipe must be installed in a continuously downward direction and in a frost free environment Water may drip from the discharge pipe of the pressure relief device and this...

Страница 10: ...e hood as it is connected to the cylinder via an earth cable and a cable to the UI The water cylinder requires two supply cables Where an off peak supply circuit is available this can be used and conn...

Страница 11: ...installation is in place it must be replaced with a single pole toggle switch which is wired from the B1 and B2 connections as shown in Figure 7 The water temperature required from the boost function...

Страница 12: ...12 Installation Figure 9 Wiring Schematic...

Страница 13: ...inlet control group flush the mains pipework out to ensure all debris has been removed so as not to damage the strainer within the combination valve 2 Make final mains connection on combination valve...

Страница 14: ...nged using the app 7 2 2 Set Hygiene Mode The cylinder heating can be controlled by a utility company via the transceiver and gateway to align heating periods with low cost electricity availability an...

Страница 15: ...Note the set pressure of the pressure reducing valve Remove cartridge and clean strainer in water provided in container Re assemble pressure reducing valve ensuring the correct pressure is set 8 Perio...

Страница 16: ...use The immersion must be switched off at the mains before draining the cylinder If replacement parts are required please see Figure 13 for part description and part numbers Waste electrical products...

Страница 17: ...17 Spare Parts 9 Spare Parts Figure 13 Replacement Part Numbers for Quantum Electric Range of Cylinders...

Страница 18: ...Data and Product Fiche 10 Technical Data and Product Fiche 50 B 635 o C D E Figure 14 Quantum Direct Electric Cylinder and Top Views For Reference Only 35 B 540 o 35 o Quantum Slimline Cylinders Quant...

Страница 19: ...c Cylinder Product Fiche Quantum Direct Electric Cylinder IOT Range Dimensions Reference QWCd125 580 IOT QWCd135 480 IOT QWCd150 580 IOT QWCd180 480 IOT QWCd210 580 IOT QWCd250 580 IOT QWCd300 580 IOT...

Страница 20: ...Heater 1 3 4 M BSP 3kW 240V Thermostatic Control Direct Input Integral immersion heater thermostat and cut out Safety Components Pressure reducing valve and strainer 3 bar Expansion relief valve 6 bar...

Страница 21: ...ture to between 45 C and 55 C Higher temperatures can introduce more heat loss from the unit and increase the risk of scalding significantly A thermostatic mixing valve should be considered When turni...

Страница 22: ...holidays selected in the timer mode menu When in No Control the cylinder heats up to the primary setpoint temperature when the supply is active off peak or during the selected off peak tariff window...

Страница 23: ...12 00 59 AM PM Date Time Set Time Set Temp Primary Set Temp Boost Primary Temperature 60 C 25 75 C Primary Set Temp Boost Boost Temperature 60 C Time Temp Time Temp Start by pressing Menu button to ac...

Страница 24: ...ightness Adjust Contrast 50 Rotate knob to adjust Display Contrast Brightness Adjust Brightness 100 Rotate knob to adjust Start by pressing Menu button to access the main menu Advance 55 C 55 C Boost...

Страница 25: ...n Menu Time Temp Function Display Main Menu Time Temp Function Display Function No Control Holiday Function Selected No Control Holiday Active Days 14 1 180 Holiday No Control Holiday Selected Figure...

Страница 26: ...Capacity Energy Current History Consumption 3000 W History Day 1 Day 1 Week Month Temperature T4 60 C T3 60 C T2 50 C T1 15 C Current Current Min Max Counter User Info Temperature Energy Counter User...

Страница 27: ...ing noise from system during re heat G 1 Air in system G 2 Flow rate well in excess of specification G 1 Bleed system thoroughly and re pressurise G 2 Reduce pump speed H Cylinder not charging H 1 Pow...

Страница 28: ...Boost temperature setpoint is too high B 2 Hygiene mode overriding primary setpoint B 3 Temperature sensors faulty or not installed correctly B 1 Check adjust the primary and boost temperature setpoin...

Страница 29: ...Energy Counter Boost 0 h 0 m Boost Primary Temperature 60 C 40 65 C Primary Set Temp Boost Boost Temperature 60 C Current History Current Capacity 5 5 kWh Hot water 125 litres Energy Current History C...

Страница 30: ...et Service Reset Hygiene RF Module Cylinder Tari Cylinder Size 125 Tari O Peak Timed Tari O Peak Timed O Peak Time Period ON23 00 OFF 07 00 RTC Calibrate Service Reset Hygiene RF Module Cylinder Tari...

Страница 31: ...31 Notes...

Страница 32: ...32 Notes...

Страница 33: ...33 Notes...

Страница 34: ...re and pressure relief valve and expansion valve been fitted and discharge tested Yes No The tundish and discharge pipework have been connected and terminated to Part G of the Building Regulations Yes...

Страница 35: ...omments Signature SERVICE 3 Date Engineer Name Company Name Telephone Number Comments Signature SERVICE 4 Date Engineer Name Company Name Telephone Number Comments Signature SERVICE 5 Date Engineer Na...

Страница 36: ...oup Ltd reserve the right to revise products literature and guarantee terms without prior notice due to a policy of continuous improvement www kiwa co uk www hotwater org uk To speak to customer servi...

Отзывы: