INSTALLATION AND OPERATION MANUAL SOLAR MODULES Q.PEAK DUO-G9.X – Q CELLS

INSTALLATION AND OPERATION MANUAL SOLAR MODULES Q.PEAK DUO-G9.X – Q CELLS

11

Module Selection

For detailed key electrical data, please refer to the actual data sheet 
referring to the relevant Module (available at www.q-cells.com).

 

Ä

For maximum energy yields, mismatches of specified electric 
current (I

MPP

) of more than 5 % should be avoided for all modules 

connected in series.

Safety Factor

During normal operation, a module may generate a greater current 
and / or higher voltage than that determined under standardized 
test conditions. Please use a safety factor of 1.25 for the following:

• 

Calculating the voltage measurement values (V

OC

) of components

• 

Calculating the current measurement values (I

SC

) of conductors

• 

Sizing of control systems connected to the outlets of the solar 
modules

 

Ä

Please follow the valid national guidelines for the installation 
of electrical systems.

Series Connection

Connection of modules in series is only permitted up to the 
maximum system voltage as listed in the applicable data sheet 
of all the relevant modules to be installed.

 

Ä

Take into account all possible operating situations and all 
relevant technical norms and regulations when designing the 
system. It has to be ensured that the maximum system voltage, 
including all necessary safety margins, is not exceeded.

 

Ä

Take the voltage limit of the inverter into account when 
determining the maximum number of modules in the string. 

Parallel Connection

Modules may be damaged by the occurrence of reverse currents 
(caused by module defects, ground leaks, or defective insulation).

 

Ä

Ensure that the maximum reverse current load capacity 
indicated in the data sheet is met.

In order to limit reverse currents that may occur, we recommend 
using the following safety options:

1) 

Layout with a limited number of 
parallel connected strings :

Without undertaking further current blocking measures, a maximum 
of two module strings may be operated in parallel on a single 
inverter or MPP tracker.

2) 

Layout with string fuses :

Use overcurrent devices (e.g. fuses) according to the relevant 
standards in each string. Use gPV-fuses according to IEC 60269-6. 
Observe the maximum permitted number of strings as indicated 
in the specifications provided by the respective string fuse 
manufacturer and the technical guidelines.

NOTE!

When installing different product versions, the lowest minimum 
permitted reverse current load capacity applies. 

Inverters

Inverters with or without transformers may be used.

2  PLANNING

2.4 ELECTRICAL LAYOUT

3  INSTALLATION

3.1  SAFETY AND TRANSPORT

 

Ä

Leave modules in their original packaging until 
installation.

 

Ä

Store the modules securely in cool and dry 
rooms. The packaging is not weatherproof.

 

Ä

Inspect the packaging for damages.

 

Ä

Contact the transport company regarding 
any damage to the packaging and follow their 
instructions.

 

Ä

Follow any instructions on the packaging.

 

Ä

Ensure that all personnel are aware of and 
adhere to accident-prevention and safety 
regulations.

 

Ä

While working wear clean gloves.

§

GB

§

I

§

D

Danger! Risk of fatal injury due to electric 
shock!

 

Ä

Do not install damaged modules.

 

Ä

Inform your distributor of any damages 
immediately.

Warning! Fire Risk!

 

Ä

Do not install modules indoors.

 

Ä

Do not install modules on moving objects.

Содержание DUO-G9 Series

Страница 1: ...INSTALLATION AND OPERATION MANUAL Q PEAK DUO G9 X solar module series Valid for Africa Europe LatinAmerica South America ...

Страница 2: ...ipulations such as country specific regulations for pressure equipment operational safety hazardous goods and environmental protection Regulations and requirements specific to the system Any applicable laws and requirements in particular inter national country specific regional laws and stipulations governing the planning installation and operation of solar power systems and work on roofs Any vali...

Страница 3: ...quirements prior to installation of the solar power system Your financial success depends on the fulfillment of these requirements Other applicable documents In addition to this Manual following technical information are relevant DOCUMENT TYPE Product data sheet Packaging and transport information Fig 1 External dimensions and components for Q PEAK DUO G9 Q PEAK DUO G9 Q PEAK DUO BLK G9 and Q PEAK...

Страница 4: ...ls to prevent contact corrosion Allows for stress free expansion and contraction due to temperature fluctuations Ä Ensure that no additional forces are applied through the mounting system into the module except for the wind and snow loads Additional forces and moments of torque at the mounting positions caused by torsions displacements or vibrations in the mounting system are not allowed Ä Ensure ...

Страница 5: ...ameters clamp width 40mm and clamp depth 10mm The system installer is responsible for the determination of location specific load requirements Ä CL1a at high loads 5400 4000Pa The clamp position is variable in the given range but the distance between the clamps along the long side of the module span must not be larger than 1070mm Ä CL1b Using of short mounting rails are permissible if they overlap...

Страница 6: ...everse currents caused by module defects ground leaks or defective insulation Ä Ensure that the maximum reverse current load capacity indicated in the data sheet is met In order to limit reverse currents that may occur we recommend using the following safety options 1 Layout with a limited number of parallel connected strings Withoutundertakingfurthercurrentblockingmeasures amaximum of two module ...

Страница 7: ...odule damage may occur Ä Never step on modules Ä Do not subject modules to any mechanical stress Ä Do not allow any objects to fall onto modules 3 INSTALLATION 3 1 SAFETY AND TRANSPORT Danger Risk of fatal injury due to electric shock Ä Block off the installation zone Ä Keep children and unauthorized individuals away from the solar power system Danger Risk of fatal injury due to electric shock Ä E...

Страница 8: ...rom the separation of a closed circuit These can result in life threatening injuries The danger increases when several modules are connected in series Ä Please be aware of that the entire open circuit voltage is active even at low levels of solar irradiation Ä Pleasefollowthevalidnationalregulationsandsafetyguidelines for the installation of electrical devices and systems Ä Please make sure to tak...

Страница 9: ...el see page 3 Ä Ensure correct polarity Ä Use solar cables for the connection at the junction box outlet Ä Only interconnect connectors of the same type and manufacturer Ä Use minimum 4mm2 copper wires insulated for a minimum of 90 C for field connections Note Module damage may occur Ä Ensure that the cabling is not under mechanical stress Comply with bending radius of 60mm Ä Ensure that the cable...

Страница 10: ...bling is not exposed and or hanging and is protected from dirt moisture and mechanical friction 4 ELECTRICAL CONNECTION 4 4 AFTER INSTALLATION Ä No dry cleaning or use of rotating brushes Ä Modules must be cleaned manually and only with sufficient water Protective Grounding Ä The modules must be grounded in accordance with the local statutory regulations DANGER Risk of fatal injury due to electric...

Страница 11: ...arry or wear any electrically conductive parts WARNING Risk of falling due to unsecured access Ä Never access the installation area alone or without taking adequate security precautions Ä Please commission a trade specialist NOTE Module surface damage may occur Ä Remove snow and ice carefully without force e g with a very soft broom Ä Do not scratch off dirt Ä Rinse dirt dust leaves etc off with l...

Страница 12: ...lee 17 21 06766 Bitterfeld Wolfen Germany TEL 49 0 34946699 23222 FAX 49 0 34946699 23000 EMAIL sales q cells com WEB www q cells com Subject to change without notice Q CELLS Installation manual solar modules Q PEAK DUO G9 X_2021 08_Rev03_EN ...

Отзывы: