Installation Guide / PostMount 1-A with ECO-Rail
10
Code-Compliant Planning and Installation Guide V 2.2 - Complying with AS/NZS1170.2: 2011 ADMT 4-2016
- Certification -
Gamcorp (Melbourne) Pty Ltd A.C.N 141 076 904 A.B.N 73 015 060 240
www.gamcorp.com.au
Suite 4, 346 Ferntree Gully Rd, Notting Hill VIC 3168 Tel: 03 9543 2211
Notes:
1. This certification is applicable for the Postmount PM1-A with dimensions as
shown in this letter.
2. Other piers dimensions are possible, contact Gamcorp, if required.
3. Panel weight calculated: 20kg.
4. Embedment depth is relevant for soils, having adhesion capacity from 300mm
of the ground level; in other cases contact Gamcorp.
5. For concrete piers foundation, use 25 MPa strength concrete (minimum). It is
recommended to insert N12 bar 200mm long at the bottom of the post into the
concrete piers.
6. If any of the above conditions cannot be met, the structural engineer must be
notified immediately.
Construction is to be carried out strictly in accordance with the manufacturers instructions and
site soil report recommendations. This work was designed by
Ali Askari
in accordance with the
provisions of relevant Regulations and in accordance with sound, widely accepted engineering
principles.
Yours faithfully,
Gamcorp (Melbourne) Pty Ltd
L. van Spaandonk
Principal Engineer
FIEAust Cpeng NER
ISO 9001:2008 Registered Firm
Certificate No: AU1222
8762 - Compliance Letter PM1-A - calc4.2.odt