5
MGH Series - Manual
Rev030921
© 2021 PS Industries
®
Incorporated. All Rights Reserved.
Installation
Step 2
Illustration I
Field Anchor
Step 3
Illustration I
(Shown as Slide Direction:
LEFT
)
DETAIL A
A
Fasteners
provided by
Installer
DETAIL B
Stop
Bracket
9
7
10
B
Line up
Edges
Operator Knockouts for use
on Electrical Gate only
View from
Mezzanine Deck
STEP 2.
Installation of Track Assembly.
a. Line up leading edge of Track Assembly with leading edge of opening.
b. Field fasten Track Assembly to your existing structure using factory located holes. (Fasteners supplied by
the Installer.)
CRITICAL
Ensure mounting surface is capable of supporting all loading. Structural analysis of mounting surface
is the responsibility of the Installer.
Fasteners must be of sufficient size, grade, appropriate for anchoring
material, etc. to accept the potential loading. Consult qualified Structural Engineer.
STEP 3.
Using supplied hardware from the Track Shroud Hardware Kit, begin assembling the Shroud Assembly
a. Install the Stop Bracket to farthest end of the Shroud Assembly using
1
/
4
” screws and flange nuts.