10
Smart Gate Series
Rev022520
© 2020 PS Industries
®
Incorporated. All Rights Reserved.
Installation
Shoulder Bolts
10.8
Step 12
Illustration A
STEP 12.
Install dampeners first into the Gate End (Illustration A), then into the slotted dampener bracket
(Illustration B) with
3
/
8
” shoulder bolts.
Step 12
Illustration B
Final operational location
Step 14
Illustration B
Step 14
Illustration A
STEP 13.
Fully extend assembly upward, anchor Gate Post back onto the floor surface, and tip gate down into Gate
Catch. As the gate approaches fully closed, you should hear a loud noise of the dampeners self-setting.
STEP 14.
Visually verify that the dampeners self-set into the appropriate location. If they did not, carefully tap them
into place with a screwdriver. (Illustration B)
DANGER
Keep fingers clear of dampener pivot points, dampeners are under high pressure.
A
DETAIL A
✘
10.5
9
10.1
10.8
10.8
10.5
Carefully
Tap
Correct