INSTALLATION
SM-PSPC5-01-E/12-2007
SERVICE MANAUL PSPC5
Page 23 of 73
PREPARATION
Before actual assembly and installation, the buyer must see to the proper preparations to facilitate
correct installation.
The connection of the system to the electricity grid has to be done by a licensed electrician.
All activities must be carried out according to local and national regulations, the requirements of the
company and the required provision for the installation.
Activities include:
- Foundations
- Power supply
- Air supply
- Clean surroundings
- Safety precautions
FACILITIES
Power supply must be conform the information on the machine tag.
Electrical cable diameter, fuses and PE connections must be in accordance with the local regulations
Facilities for air must be in a clean condition.
The supplied air must be clean and according the requirements.
The floor must be flat and smooth with sufficient bearing power.
The climate around the machine must have a normal working temperature (+10ºC to 30ºC).
INSTALLATION DATA
Weight:
Packer
: Approximately 500 kg
Output conveyor
: Approximately 100 kg
Electrical data:
Connection voltage
: 400V 3 phase + N + PE 50Hz
Connection
:
5x2,5
mm²
Pre fuse 3 phase
: 16 Amp, slow blowing
Pre fuse 1 phase
: 25 Amp
Earth leak protection
: A minimum leakage current of 200 mA (inverter)
Power
:
1.5
kW
Maximum voltage deviation
: -6% to +10%.
Electrical protection
: IP55
Other possible connections
: 3 phase + N + PE 50 Hz
3 phase + PE 50 Hz
1 phase + N + PE 50 Hz
Power 400/230V = 400 V phase voltage, 230 line voltage.
Power 230V = 230 V phase voltage or 230 V line voltage.
Pneumatic data:
Air consumption
: 11 normal Litre/minute
Air pressure
: in between 8 and 10 bars (System air regulator reduces it to 6
bars)
Connection
:
13
mm
Содержание PSPC5
Страница 2: ......
Страница 4: ......
Страница 7: ...INTRODUCTION SM PSPC5 01 E 12 2007 SERVICE MANAUL PSPC5 Page 7 of 73 INTRODUCTION...
Страница 14: ......
Страница 15: ...SAFETY SM PSPC5 01 E 12 2007 SERVICE MANAUL PSPC5 Page 15 of 73 1 SAFETY...
Страница 20: ......
Страница 21: ...INSTALLATION SM PSPC5 01 E 12 2007 SERVICE MANAUL PSPC5 Page 21 of 73 2 INSTALLATION...
Страница 33: ...COMPONENTS ADJUSTMENTS SM PSPC5 01 E 12 2007 SERVICE MANAUL PSPC5 Page 33 of 73 3 COMPONENTS ADJUSTMENTS...
Страница 37: ...PACKER SM PSPC5 01 E 12 2007 SERVICE MANAUL PSPC5 Page 37 of 73 4 PACKER...
Страница 52: ......
Страница 53: ...OUTPUT CONVEYOR SM PSPC5 01 E 12 2007 SERVICE MANAUL PSPC5 Page 53 of 73 5 OUTPUT CONVEYOR...
Страница 58: ......
Страница 59: ...30 CELL TRAY DENESTER SM PSPC5 01 E 12 2007 SERVICE MANAUL PSPC5 Page 59 of 73 6 30 CELL TRAY DENESTER...
Страница 64: ......
Страница 65: ...HATCH TRAY DENESTER SM PSPC5 01 E 12 2007 SERVICE MANAUL PSPC5 Page 65 of 73 7 HATCH TRAY DENESTER...
Страница 70: ......
Страница 71: ...TROUBLE SHOOTING GUIDE SM PSPC5 01 E 12 2007 SERVICE MANAUL PSPC5 Page 71 of 73 8 TROUBLE SHOOTING GUIDE...