NB City
POWER ELECTRONICS
40
MAINTENANCE
Checklist
The list of tasks detailed below should be carried out annually. The time of each task is an estimate.
MAINTENANCE
TIME
GLOBAL OPERATION TIME
1h and 55min
The following tasks must be performed with the equipment completely off (no voltage at all, stopped,
uncharged and isolated):
POWER TEST (STATUS 1)
TIME
(MINUTES)
OK
1
Environmental conditions
–
Visual check
5
2
Enclosure state
–
Visual check
5
3
Make sure the charger is accessed remotely - connection to the PC if it exists.
5
4
Display operation, if it exists - visual and manual check
5
5
Ventilation system and absence of vibrations - visual and auditory check
5
6
Charge connector operation - visual and manual check
5
7
Charge test recommended (optional)
10
8
Operation of the differential switch - Visual and manual check
5
DEAD TEST (STATUS 2)
TIME
(MINUTES)
OK
1
Internal cleaning
15
2
Filters - visual check and replacement
15
3
Doors condition
10
4
Cables and conductors - visual and manual check
10
5
External and internal tightening torques - manual check
10
6
Control circuit and protections - manual check
10
Содержание NB CITY
Страница 1: ...NB CITY HARDWARE AND INSTALLATION MANUAL ELECTRICAL VEHICLES CHARGING SOLUTIONS...
Страница 2: ......
Страница 3: ...NB City EV CHARGING SOLUTIONS Hardware and Installation Manual Edition April 2020 NBCHW01CI Rev C...
Страница 45: ...CE_NB50_REV0_11122019 www power electronics com EN...
Страница 46: ...CE_NB50_REV0_11122019 www power electronics com...
Страница 47: ......
Страница 48: ...24H TECHNICAL ASSISTANCE 365 DAYS A YEAR FIND YOUR NEAREST DELEGATION POWER ELECTRONICS COM CONTACT...