The positioning of the cable pit for the PARVIS
column, once assembled, takes place through
the masonry keeping the upper edge flush with
the ground.However, it is possible to keep the
upper edge a few centimetres below ground
level, in order to partially cover the base of the
column with earth.
6.2 Cable pit positioning
Positioning must take place perpendicular to
the ground.If the base is not perfectly level,
minor adjustments can be made by adjusting
the inserts on the cable pit.By loosening the
insert on the appropriate side to be corrected,
the PARVIS base is raised to achieve the
appropriate vertical alignment.