FOOTING NOTES (IN GROUND)

•  Support post footing depth equals 42 in. (1067 mm) minus the depth of the 

protective surfacing material. The posts are designed to have 24" (610 mm) in 
concrete. 

 

Example:

 If 12 in. (305 mm) of wood mulch is used for surfacing, the footing 

depth would be 30 in. (762 mm). 

•  GroundZerO

®

 support post footing depth equals 54 in. (1372 mm) minus the 

depth of the protective surfacing material. The posts are designed to have 36" 
(914 mm) in concrete. 

 

Example:

 If 12 in. (305 mm) of wood mulch is used for surfacing, the footing 

depth would be 42 in. (1067 mm). 

•  Most support posts and component support legs will have either a factory-applied 

sticker with a line, or factory-applied mark designating the level of protective 
surfacing on a clear and level installation site. The footing depth measurements 
are based on this line/mark. 

•  If the play equipment is installed on uneven terrain, maintain support post mark 

for  the  protective  surfacing  level  at  the  lowest  grade. Adjust  other  footings 
accordingly. Support posts and all attaching decks and play components must 
be plumb and level.

•  Do not encase the bottom of the support post in concrete. Place the post directly 

on packed stone or other porous material.

•  The footings shown on Playworld Systems’ documentation are recommendations 

based on historical performance in average soil conditions. Footing dimensions 
may be modifi ed by the owner based on actual soil conditions.  

For example:
  - If local soil is loose or unstable, a larger footing may be required. 
  - If local soil is considered stable, such as bedrock, clay or hard packed earth, a 

smaller footing may be used. Before changing footing dimensions, we strongly 
recommend  that  the  footings  be  reviewed  and  approved  by  a  registered 
engineer.

•  The base of the footing must be below the frost line.

•  Assemble  the  entire  structure  before  pouring  concrete  unless  specifi cally 

instructed to do so in the installation instructions.

Footing Details (in ground)

2" (51 mm)

18"

(457 mm)

Diameter

Varies

42"

(1067 mm)

Varies

36"

(914 mm)

Ground Level

Concrete

Protective Surfacing Level

Factory-Applied Protective 
Surfacing Level Sticker

Support Post

Block

Porous Material

Support Post Footing Detail (ASTM/CSA)

Block Option

2" (51 mm)

18"

(457 mm)

Diameter

Varies

54"

(1372 mm)

Varies

48"

(1219 mm)

GroundZerO

®

 Support Post Footing Detail ASTM/CSA

Block Option

Ground Level

Concrete

Protective Surfacing Level

Factory-Applied Protective 
Surfacing Level Sticker

Support Post

Block

Porous Material

Footing Notes

Содержание Cozy Cocoon

Страница 1: ...allation Time 1 5 man hours Concrete Required 0 13 cubic yard 0 10 cubic meters Use Zone Refer to information below User Group Age years ASTM CSA 2 12 EN 2 14 ICON KEY Fully Tighten Hardware Add 1 Dro...

Страница 2: ...stallation Instructions Model XX0483 PA1380 Page 2 of 8 685 1 9 Top View Elevation Views Footing Diagram ASTM CSA 14 356 mm EN 48 4 1245 mm KEY Position Unit of Measurement Top Inches Bottom Millimete...

Страница 3: ...er Casting AAU0718 1 Total Cocoon Half BPL3150 1 Total 3 8 x 2 3 4 Button Head Bolt BAE06677 3 Total 3 8 Button Head Nut BAE0663 3 Total Plastic Washer BPL0300 3 Total 3 8 Flat Washer BAE0595 3 Total...

Страница 4: ...Button Head Nut BAE0663 4 Total 3 8 Flat Washer BAE0595 4 Total 3 8 x 3 4 Button Head Bolt BAE0659 4 Total Detail C Step 6 Attach the cocoon support post to the cocoon post casting 3 8 x 2 3 4 Button...

Страница 5: ...s Snug tighten and then tighten an additional one half turn Step 5 Attach the cocoon halves together See Detail B Place the two cocoon halves together and attach as shown Fully tighten the connections...

Страница 6: ...6 x 1 63 BARREL 8 BAE0659 BOLT 3 8 16 x 3 4 BUTTON HEAD S S 4 BAE0663 NUT 3 8 16 x 7 16 BUTTON HEAD 10 BAE06675 BOLT 3 8 16 x 2 1 4 BUTTON HEAD S S 8 BAE06677 BOLT 3 8 16 x 2 3 4 BUTTON HEAD S S 6 BAE...

Страница 7: ...ks or breakage If any damage is detected barricade the equipment to prevent use until repair is completed Contact your sales representative immediately for a replacement part Welds Inspect all welded...

Страница 8: ...ke Repairer Name Please Print __________________________________ Signature ________________________________________ Date ___ ___ ___ MAINTENANCE SCHEDULE Item in Question Description of Problem Correc...

Страница 9: ...rfacing If adjacent play structures have a fall height greater than 30 inches 760 mm than the distance between the structures shall be no less than 108 in 2743 mm CSA compliance For rotating play equi...

Страница 10: ...commonly used hex key wrenches required to assemble your equipment You may also need shovel digging iron post hole digger steel rake wheelbarrow garden hoe water hose tape measure level alignment tool...

Страница 11: ...aries 36 914 mm Support Post Footing Detail ASTM CSA Ground Level Concrete Protective Surfacing Level Factory Applied Protective Surfacing Level Sticker Support Post 2b Stone End Cap from Post Shippin...

Страница 12: ...he support post in concrete Place the post directly on packed stone or other porous material The footings shown on Playworld Systems documentation are recommendations based on historical performance i...

Страница 13: ...est grade Adjust other footings accordingly Support posts and all attaching decks and play components must be plumb and level The footing size may vary due to local soil and weather conditions Base of...

Страница 14: ...ght dimensions Height measurements are taken from the top of the protective surfacing material Insure all fasteners are tightened according to tightening torque speci cations listed on your installati...

Отзывы: