Modes of Operation
Auto Test Modes (continued)
Weekly Test
The weekly test is performed each Monday at 03:00 A.M. If the defibrillator is in
use, the test will be performed at 03:00 A.M. the following week. The weekly test
consists of an initialization test.
Monthly Test
The monthly test is performed on the first Monday of each month at 03:00 A.M. if
the defibrillator is in use, the test will be performed at 03:00 A.M the following
month. If a weekly test and a monthly test are scheduled to occur at the same
time, the monthly test will occur.
WARNING!
Shock Hazard.
During the monthly auto test, the defibrillator will
automatically charge the main capacitor. Do not attempt to disassemble
the defibrillator.
In addition to performing an initialization test, the monthly test evaluates the
following circuits and systems:
–
ECG/impedance
–
High-voltage charging system and discharge circuit
–
Power system
(Continued on next page)