 AIR PURGING

When Using the Vacuum Pump

(For method  of using a  manifold valve, refer 
to its operation manual.)
1. Completely tighten the flare nuts, A, B, C, D, 
    connect the manifold valve charge hose to a 
    charge port of the low-pressure valve on the 
    gas pipe side.
2. Connect the charge hose connection to the 
    vacuum pump.
3. Fully open the handle Lo of the manifold valve.
4. Operate the vacuum pump to evacuate. After 
    starting evacuation, slightly loosen the flare nut 
    of the Lo valve on the gas pipe side and 
    check that the air is entering (operation noise 
    of  the vacuum pump changes and a 
    compound meter indicates 0 instead of minus).
5. After the evacuation is complete, fully close 
    the handle Lo of the manifold valve and stop 
    the operation of the vacuum pump. Make 
    evacuation for 15 minutes or more and check 
    that the compound meter indicates 

5

    -76cmHg  (-1x10 Pa).
6. Turn the stem of the packed valve B about 

o

    45  counterclockwise for 6~7 seconds after 
    the gas coming out, then tighten the flare nut 
    again. Make sure the pressure display in the 
    pressure indicator is a little higher than the 
    atmosphere pressure.
7. Remove the charge hose from the Low 
    pressure charge hose.
8. Fully open the packed valve stems B and A.
9. Securely tighten the cap of the packed valve.

Manifold valve

Compound meter

-76cmHg

Handle Lo

Handle Hi

Charge hose

Charge hose

Vacuum pump

Pressure gauge

Low pressure valve

Fig.67

Perform the electric safe check after 
completing installation:
1. Insulated resistance
    The insulated resistance must be more than 2M .
2. Grounding work 
    After finishing grounding work, measure the 
    grounding resistance by visual detection and 
    grounding resistance tester. Make sure the 
    grounding resistance is less than 4 . 
3. Electrical leakage check (performing during 
    test running)
    During test operation after finishing installation, 
    the serviceman can use the electroprobe and 
    multimeter to perform the electrical leakage 
    check. Turn off the unit immediately if leakage 
    happens. Check and find the solution 
    until the unit operates properly.

    Electrical safety check

Safety and leakage check

Indoor unit 

check point

Outdoor unit 

check point 

n m k

j i h

A

B

C

a

c

b

d

e

f

Fig.68

Содержание 1PAMSCH12

Страница 1: ...er please read this manual carefully and keep it for future reference along with your receipt ROOM AIR CONDITIONER Before using your air conditioner please read this manual carefully and keep it for f...

Страница 2: ...e that they do not play with the air conditioner Replacement work shall be performed by authorized personnel only Installation work must be performed in accordance with the national wiring standards b...

Страница 3: ...d regulation and these installation instructions An independent circuit and single outlet must be used If electrical circuit capacity is not enough or defect found in electrical work it will cause ele...

Страница 4: ...t radiation from the condenser is not restricted Ensure that the clearance around the back of the unit is more than 12 inches 30cm and left side is more than 12 inches 30cm The front of the unit shoul...

Страница 5: ...ize 1 4 6 35mm 3 8 9 53mm 1 2 12 7mm 6 2 Self tapping Screw B ST2 9X10 Remote Control Installation Plate Name of Part Self Tapping Screw A ST3 9X25 Seal for cooling heating models only Drain Joint Tra...

Страница 6: ...ctions should be free from obstructions CAUTION INSTALLATION INSTRUCTIONS 5 CAUTIONS One Two Zone One Three Zone One Four Zone More than 4 73in 12cm r e t l i f r i A Remote control n i 3 7 4 n a h t...

Страница 7: ...ly to outdoor side 3 Connective Pipe and Drainage Installation 1 Run the drain hose sloping downward Do not install the drain hose as illustrated in Fig 7 Drainage Fig 7 Do not block water flow by a r...

Страница 8: ...drain hose with tape securely evenly as shown in Fig 11 Because the condensed water from rear of the indoor unit is gathered in evaporative drain pain box and is piped out of room do not put anything...

Страница 9: ...nit and the wall Remove after finished piping 4 Push the lower part of the indoor unit up on the wall then move the indoor unit from side to side up and down to check if it is hooked securely 4 Indoor...

Страница 10: ...e installation board Drill four holes of 0 5 inches 12mm 2 5 inches 50 55mm deep at the selected positions on the ceiling Then embed the expansible hooks fittings Face the concave side of the installa...

Страница 11: ...r 3 8 inches 10 12mm Refer to Fig 17 2 Install The Panel 1 Remove the inlet grid CAUTIONS a Slide two grid switches toward the middle at the same time and then pull them up Refer to Fig 21 o b Draw th...

Страница 12: ...s outlet has been reduced to about 0 16 0 24 inches 4 6mm The edge of the panel should contact with the ceiling well Refer to Fig 24 Do not over tighten the screw Fig 25 If the gap between the panel...

Страница 13: ...rge Before installing condensate water pipeline determine its route and elevation to avoid intersection with other pipelines and ensure slope is straight Support drain link per code The drainage pipe...

Страница 14: ...e Drain tee Water flow Water flow Water flow Water flow Water flow Water flow Water flow Water flow Drain tee Water flow Water flow Keep a certain degree Branch pipe Branch pipe Gas Gas Main pipe Main...

Страница 15: ...units The drainage pipe should be set down inclined after the lifting pipe immediately to avoid wrong operation of water level switch Refer to the following picture for installation reference 4 Liftin...

Страница 16: ...ed suspending installation the installation bracket should accord with technique requirement in the installation bracket diagram The installation wall should be solid brick concrete or the same intens...

Страница 17: ...an the measured distance 4 Cut the cable 59 1 inches 1 5m longer than the pipe length 1 Flaring work Fig 53 B Burr removal 1 Completely remove all burrs from the cut cross section of pipe tube 2 Put t...

Страница 18: ...tage should be in the range of 90 110 of rated voltage 3 The creepage protector and main power switch with a 1 5 times capacity of Max Current of the unit should be installed in power circuit 4 Ensure...

Страница 19: ...ed The power is supplied from the Outdoor Unit The Indoor Units are connected with signal wires or power cords are connected reliably and correctly or the air conditioner could not run normally Fig 62...

Страница 20: ...3 S A L A N A L C N C S C L B N B S B L A N A S A L B L C L D N B N D N C S C S D S B NOTE please refer to the following figures if the client wants to wire by themselves ELECTRICAL WORK 19 Model A Mo...

Страница 21: ...of power source 4 Confirm that electrical capacity is sufficient 5 See to it that the starting voltage is maintained at more than 90 percent of the rated voltage marked on the name plate 6 Confirm tha...

Страница 22: ...the outdoor unit Note that both the liquid and the gas side service valves on the outdoor unit are kept closed at this stage Pipe length and refrigerant amount Connective pipe length Less than 16 41 f...

Страница 23: ...flare nut again Make sure the pressure display in the pressure indicator is a little higher than the atmosphere pressure 7 Remove the charge hose from the Low pressure charge hose 8 Fully open the pa...

Страница 24: ...e nut connections and electrical safety check Check that all tubing and wiring have been properly connected Check that the gas and liquid side service valves are fully open 1 Connect the power press t...

Отзывы: