A. 

Remove all packaging from the window.

B. 

REPLACEMENT APPLICATIONS: 

Remove the 

existing, window, trim, insulation and sealant from the 
opening.

1

ROUGH OPENING PREPARATION

C. 

NEW CONSTRUCTION APPLICATIONS: 

Cut the 

water resistive barrier. Fold the side flaps into the opening 
and staple to inside wall. 

YOU WILL NEED TO SUPPLY:

TOOLS REQUIRED:

• Impervious Shims/Spacers (12 to 20)
• Finish nails, 1" brads
• 3/16" x 2-1/2" concrete screws (for masonry installation)
• Closed cell foam backer rod/sealant backer (12 to 30 ft.)
• Pella

®

 SmartFlash

 foil backed butyl window and 

door flashing tape or equivalent

• Great Stuff 

 Window and Door Insulating Foam 

Sealant by the Dow Chemical Company or equivalent  
low pressure polyurethane window and door foam -  
DO NOT use high pressure or latex foams.

• OSI Quad Multi-Polymer sealant or equivalent high  

quality exterior grade polyurethane or silicone sealant.  
(1 tube per window)

• Tape measure
• Level
• Square
• Hammer or Finish Nailer 
• Stapler
• Scissors or utility knife
• Drill with a #2 Phillips (at least 

4" long) and #3 square drive bit 
(provided in cable clamp kit)

• 1/2" open end wrench
• 3/16" wrench or socket
• Sealant Gun

Installation will require two or more persons for safety reasons.

4&"-"/5

4&"-"/5

REMEMBER TO USE APPROPRIATE PERSONAL PROTECTIVE EQUIPMENT.

Interior 

1D

1st cut 

2nd 

cut 

3rd cut 

Water Resistive Barrier 

1

1E

D. 

Confirm the window will fit the opening

. Measure all 

four sides of the opening to make sure it is 3/4" larger 
than the window in both width and height. Measure the 
width and height in several places to ensure the header 
and studs are not bowed.

Note: 1-1/2" or more of solid wood blocking is required 
around the perimeter of the opening. Fix any problems 
with the opening before proceeding. If installing new 
blocking, install the blocking so it’s flush with the 
exterior sheathing of the house. DO NOT attempt to 
install a window in an under size opening.

E. 

Confirm the opening is plumb and level

.

Note:  It is critical the bottom is level.

LEGEND - STEPS REQUIRED OF:

NEW

 

CONST

REPL

 

APPS

ALL

ALL

ALL

ALL

ALL

ALL

ALL

ALL

ALL

ALL

ALL

= All applications

REPL

 

APPS

= Replacement applications

NEW

 

CONST

= New Construction applications

Содержание 81470102

Страница 1: ...ion in a wall system designed to manage water These instructions are not to be used with any other construction method Installation instructions for use with other construction methods multiple units...

Страница 2: ...knife Drill with a 2 Phillips at least 4 long and 3 square drive bit provided in cable clamp kit 1 2 open end wrench 3 16 wrench or socket Sealant Gun Installation will require two or more persons for...

Страница 3: ...k and rough opening Apply sealant at each joint between the brick blocking and rough opening and cover the joints with flashing tape H Apply sill flashing tape 1 Wood wall construction only Cut a piec...

Страница 4: ...tape 2 Cut a piece of flashing tape 12 longer than the opening width Apply at the bottom overlapping tape 1 by at least 1 DO NOT allow the tape to extend past the interior face of the opening Note The...

Страница 5: ...Check window for squareness by making sure diagonal measurement for corner to corner is within 1 8 in both directions Insert a 10 x 3 flat head wood screw into each pre drilled hole in the jamb boards...

Страница 6: ...etween the rafter tails directly above the cable holes in the bay bow head board B Remove the cable from the bay bow unit Measure the distance from the bottom of the cable clamp to the bottom of the h...

Страница 7: ...put on the seat board knee braces must be used in addition to the cables HEAD BOARD SEAT BOARD 18 PROJECTION MAXIMUM DASHED LINES INDICATE POSSIBLE CONSTRUCTION FOR GABLE ROOF MINIMUM 10 1 2 HEADER MO...

Страница 8: ...space between the window and the rough opening and apply a 1 deep bead of foam This will allow room for expansion of the foam and will minimize squeeze out If using foam other than Great Stuff Window...

Страница 9: ...Foam BRICK FRAMED REPLACEMENT 3 8 Clearance Backer Rod and Sealant typical Insulating Foam BRICK SMALL BLOCK REPLACEMENT Air Gap Block 1 x 2 Sheet Rock Lathe Plaster Insulating Foam 3 8 Clearance Bac...

Страница 10: ...ween the frame expander and the under side of the seat board F Shape tool and clean excess sealant When finished the sealant should be the shape of an hourglass Note This method creates a more flexibl...

Страница 11: ...cess sealant When finished the sealant should be the shape of an hourglass Note Backer rod adds shape and depth for the sealant line This method creates a more flexible sealant line capable of expandi...