TWO OR MORE PEOPLE WILL BE REQUIRED FOR THE FOLLOWING STEPS.

3

SETTING AND FASTENING THE WINDOW

A. 

Insert the window

 from the exterior of the building. 

Place the bottom of the window on the spacers at 
the bottom of the opening, then tilt the top into 
position. Center the window between the sides of the 
opening to allow clearance for shimming, and insert 
one roofing nail in the first hole from the top of each 
jamb nailing fin. These are used to hold the window 
in place while shimming it plumb and square.

B. 

Plumb and square window.

 Place shims between 

the window frame and the rough opening at each 
installation screw hole. Adjust the shims as required 
to plumb and square the window in the opening.

Note: DO NOT over shim.

C. 

Check the interior reveal.

 Make sure the 

measurement from the interior face of the window to 
the interior face of the wall is equal at several points 
around the window.

Note: If the dimensions are not equal, check 
to make sure the fins are folded out to 90° at 
all points.

D. 

Fasten the window to opening.

 On windows with a fixed 

EXTRUDEDlNDRILLDIAMETERHOLESINTHElN

EVERY$RIVEAGALVANIZEDROOlNGNAIL

INTOEACHOFTHEPREPUNCHEDANDPREDRILLED

holes. 

 

For flexible fins:

 Drive nails until the head 

contacts the fin, however DO NOT sink 
the head. This allows for movement of 
building materials.

Note: Make sure the fin corner is lying as 
flat as possible.

"

*OUFSJPS

   

   

   

*/$)&4

NN

$

#

&YUFSJPS

%

%

Содержание 80GZ0102

Страница 1: ...ting an experienced architect contractor or structural engineer prior to installation of Pella products The individual building owner architect contractor installer and or consumer responsible for the...

Страница 2: ...E APPROPRIATE PERSONAL PROTECTIVE EQUIPMENT B Verify the window will t the opening Measure all four sides of the opening to MAKE SURE IT IS LARGER THAN THE WINDOW in both width and height On larger op...

Страница 3: ...G from each side Spacers are also required at points where windows are joined in multiple window applications Add shims as necessary to ensure the spacers are level Once level attach spacers and shims...

Страница 4: ...each installation screw hole Adjust the shims as required to plumb and square the window in the opening Note DO NOT over shim C Check the interior reveal Make sure the measurement from the interior fa...

Страница 5: ...dow Position the tape so it laps ONTO THE FRAME CLADDING COVERS THE lN AND LAPS ONTO THE WATER RESISTIVE BARRIER 4HE TAPE SHOULD EXTEND ABOVE THE TOP OF THE WINDOW AND BELOW THE BOTTOM OF THE WINDOW 0...

Страница 6: ...al cuts in the water resistive barrier Apply the tape covering the entire diagonal cut in the resistive water barrier at both upper corners of the window Note Be sure to overlap the top corners 4E 5 S...

Страница 7: ...PG DDFTTPSZ SPPWF DDFTTPSZ SPPWF OTVMBUJOH GPBN JO 7 45 4 JO MFBSBODF BDLFS 3PE BOE 4FBMBOU UZQJDBM OTVMBUJOH GPBN 1FSJNFUFS 4FBMBOU NVTU FYUFOE UP SPPNTJEF PG DDFTTPSZ SPPWF DDFTTPSZ SPPWF 7 INTERIO...

Страница 8: ...e the sash to stick it is optional to paint stain or nish the HORIZONTAL SASH EDGES s N PATIO DOORS IT IS OPTIONAL TO PAINT STAIN OR lNISH THE VERTICAL AND HORIZONTAL PANEL EDGES Note To maintain prop...

Страница 9: ...lla products as well as the design and installation of ashing and sealing systems are the responsibility of the Buyer or User the architect contractor installer or other construction professional and...

Отзывы: