background image

YOU WILL NEED TO SUPPLY:

TOOLS REQUIRED:

s#EDAROR)MPERVIOUSSHIMSSPACERSTO 
sGALVANIZEDROOlNGNAILSLB 
s#LOSEDCELLFOAMBACKERRODSEALANTBACKERTOFT 
s0ELLA

®

 SmartFlash

 foil backed butyl window and door  

flashing tape or equivalent

s(IGHQUALITYEXTERIORGRADEPOLYURETHANEORSILICONESEALANT

 

TUBEPERWINDOW 

s'REAT3TUFF

 Window and Door Insulating Foam Sealant 

by the Dow Chemical Company or equivalent low pressure 
polyurethane window and door foam - DO NOT use high 

PRESSUREORLATEXFOAMS

s)NTERIORTRIMANDORJAMBEXTENSIONSTOFT 

s4APEMEASURE

s,EVEL

s3QUARE

s(AMMER

s3TAPLER

s3CISSORSORUTILITYKNIFE

s3MALLmATBLADESCREWDRIVER

s3EALANTGUN

SEALANT

SEALANT

REMEMBER TO USE APPROPRIATE PERSONAL PROTECTIVE EQUIPMENT.

1

 ROUGH OPENING PREPARATION

A. 

Verify the opening is plumb and level.

Note: It is critical that the bottom is level.

B. 

Verify the window will fit the opening.

 

Measure all four sides of the opening to make 

SUREITISLARGERTHANTHEWINDOWIN

both width and height. On larger openings 
measure the width and height in several 
places to ensure the header or studs are not 
bowed.

Note: 1-1/2" or more of solid wood blocking 
is required around the perimeter of the 
opening. Fix any problems with the rough 
opening before proceeding.

Interior 

1A

Interior

1B

C. 

Cut the water resistive barrier

#

D. 

Fold the water resistive barrier

$ &OLDSIDEmAPSINTOTHE

opening and staple to inside wall. Fold top flap up and temporarily 
fasten with flashing tape.

1D

Exterior

4th cut: 

Make a 6" cut up from 

each top corner at a 45o 

angle to allow the water 

resistive barrier to be 

lapped over the fin at the 

head of the window. 

1st cut

2nd

cut

3rd cut

Water Resistive Barrier

1C

Содержание 801P0101

Страница 1: ...ue to your project may require an installation method different from these instructions and additional care Determining the appropriate installation method is the responsibility of you your architect...

Страница 2: ...1 ROUGH OPENING PREPARATION A Verify the opening is plumb and level Note It is critical that the bottom is level B Verify the window will t the opening Measure all four sides of the opening to make S...

Страница 3: ...grilles or hardware are removed from the window at this time label them and store them in a protected area 1 ROUGH OPENING PREPARATION CONTINUED F Tab the sill ashing tape and fold UT WIDE TABS AT EAC...

Страница 4: ...bottom and top of the window between the window and the sides of the opening Adjust the shims as required to plumb and square the window in the opening If the frame height EXCEEDS PLACE SHIMS AT THE...

Страница 5: ...ration VENT UNITS ONLY BY OPENING AND CLOSING the window Note If the window does not operate correctly check to make sure it is still plumb level square and that the sides are not bowed If adjustments...

Страница 6: ...Perimeter Sealant must extend to room side of Accessory Groove Accessory Groove Sealant typical 3 8 Min 3 8 BRICK VENEER 3 8 Clearance Backer Rod and Sealant typical Perimeter Sealant must extend to...

Страница 7: ...use tools that might damage the surface 5SE OF INAPPROPRIATE lNISHES SOLVENTS BRICKWASH OR CLEANING CHEMICALS WILL CAUSE ADVERSE reactions with window and door materials and voids the Limited Warrant...

Страница 8: ...NAL INSTALLATION FOLD THE CRANK OVER AND snap the knob into the pocket Note Even with the window open the crank can be folded to avoid interfering with the window treatments Crank Handle C D Operator...

Отзывы: