3. Managing burner combustion test at high fire (100%
Modulation):
a.
ON THE MANAGING BURNER
, enter the
“Installer Menu” by pressing and holding the
“Select” & “Menu” keys simultaneously for 3
seconds.
b. Use the “
ò
” key to scroll down until the cursor
( ) is at “System Test”. Press “Select”.
c. Use the “
ò
” key to scroll down to “High Power”.
Pressing select will initiate the burner operation.
d. The burner will ignite and, after a short
stabilization period, run at 100% of modulation.
If the supply temperature exceeds the setpoint (or
the boiler design temperature if an outdoor reset
CH mode is chosen) the burners will shut down.
e. Using a suitable combustion analyzer (Testo 330-2
or equivalent) determine the exhaust emissions of
the boiler.
f. Use Table 5.5, Combustion Settings, to determine
the appropriate emissions levels.
g. If the emissions are incorrect, adjust the
throttle screw to correct the combustion.
Note that increasing the throttle adjustment
(counterclockwise) will decrease the O
2
and
increase the CO
2
. Decreasing the throttle will have
the opposite effect.
4. Managing burner combustion test at low fire (1%
modulation):
a. Enter the “Installer Menu” and choose “System
Test”. Press “Select”.
b. Use the “
ò
” key to scroll down to “Low Power”.
Pressing select will initiate the burner operation.
c. The burner will ignite and, after a short
stabilization period, run at 1%.
d. Using a suitable combustion analyzer (Testo 330-2
or equivalent) determine the exhaust emissions of
the boiler and compare them with Table 9.1.
e. Do not make throttle adjustments in Low Power
system test. If the low fire values are out of
specification, contact your PB Heat representative.
5. Dependent burner combustion test at high fire (100%
modulation).
a.
ON THE DEPENDENT BURNER
enter the
“Installer Menu” and choose “System Test”.
b. Press select and use the “
ò
” key to scroll down to
“High Power”.
c. The burner will ignite and, after a short
stabilization period, run at 100%.
d. Using a suitable combustion analyzer determine
the exhaust emissions of the boiler and compare
them with Table 9.1.
e. Adjust the throttle screw if necessary to correct the
combustion.
6. Dependent burner combustion test at low fire (1%
modulation).
a.
ON THE DEPENDENT BURNER
, enter the
“Installer Menu” and choose, “System Test”.
b. Press select and use the “
ò
” key to scroll down to
“Low Power”.
c. The burner will ignite and, after a short
stabilization period, run at 1%.
d. Using a suitable combustion analyzer (Testo 330-2
or equivalent) determine the exhaust emissions of
the boiler and compare them with Table 9.1.
e. Do not make throttle adjustments in Low Power
system test. If the low fire values are out of
specification, contact your PB Heat representative.
7. Turn “System Test” to “Off” on both burner displays.
G. TEST OPERATING LIMIT
Check that each burner will shut down when the supply
water temperature reaches the control se 9°F (5°C).
1. On the LCD display for each burner, note the boiler
setpoint by accessing the User Menu, Status Display.
a. Press the “Menu” key on the keypad.
b. Choose “Status” by pressing the “Select Key”.
c. Use the “
ñ
” and “
ò
” key to scroll through the CH
and DHW setpoints (Refer to Appendix B for an
overview of the User Menu).
2. Enter the “Installer Menu” by pressing and holding the
“Select” & “Menu” keys simultaneously for 3 seconds.
a. Use the “
ò
” key to scroll down until the cursor
(
) is at “System Test”.
b. Press select and use the “
ò
” key to scroll down to
“High Power”.
c. The burner will ignite and, after a short
stabilization period, run at 100%.
3. Monitor the boiler temperature on the temperature
gauge (factory supplied for field mounting) and on the
Status display.
a. The boiler should shut down at the boiler setpoint
plus 9°F (5°C).
b. If it does not shut down turn off the boiler and
contact your PB Heat representative.
Be sure that the dependent burner is not running
when performing the combustion test on the
managing burner. If the other blower is running, the
test results will not be valid.
NOTICE
Be sure that the managing burner is not running
when performing the combustion test on the
dependent burner. If the other blower is running, the
test results will not be valid.
NOTICE
START-UP PROCEDURE
Содержание PUREFIRE PFC-1000
Страница 1: ...PUREFIRE Boilers PFC 850 PFC 1000 PFC 1500 Gas Installation Operation Maintenance Manual ...
Страница 23: ...21 WATER PIPING CONTROLS Figure 4 4 Recommended Piping One Boiler with Multiple CH Zones One DHW Tank ...
Страница 24: ...22 WATER PIPING CONTROLS Figure 4 5 Recommended Piping Multiple Boilers with Multiple CH Zones One DHW Tank ...
Страница 62: ...60 START UP PROCEDURE J LIGHTING OPERATING INSTRUCTIONS Figure 9 1 Lighting Operating Instructions ...
Страница 80: ...78 REPAIR PARTS Figure 13 3a Jacket Assembly PFC 850 1000 Figure 13 3b Jacket Assembly PFC 1500 ...
Страница 82: ...80 Figure 13 4 Control System REPAIR PARTS ...
Страница 84: ...82 Figure 13 5 Condensate System REPAIR PARTS ...
Страница 89: ...87 APPENDIX B BURNER LCD STATUS SCREENS CH Burn Cycle DHW Burn Cycle Special Functions DHW Tank Warm Hold ...
Страница 90: ...88 APPENDIX C USER MENU APPENDIX C USER MENU Figure C 1 User Menu Managing Burner ...
Страница 91: ...89 APPENDIX C USER MENU Figure C 1 User Menu Dependent Burner ...
Страница 92: ...90 APPENDIX D INSTALLER MENU STRUCTURE APPENDIX D INSTALLER MENU STRUCTURE ...
Страница 93: ...91 APPENDIX D INSTALLER MENU STRUCTURE ...
Страница 95: ...93 SERVICE LOG SERVICE LOG Date Serviced By Description of Service Serial Number ...
Страница 96: ...94 NOTES ...
Страница 97: ...95 NOTES ...