5 Assembly and installation
14
996098460-mub-en – V02
2016/05
Top view
1.
Determine the mounting location of the transfer station near the buffer tank.
In long pipes, the transmission performance may be reduced due to higher
pressure losses.
2.
Remove the packaging.
3.
Take the stations off the pallet.
4.
Mount the enclosed stand feet to compensate the unevenness of the floor.
5.
Position both modules side by side.
Note: The insulation between the frames remains mounted!
6.
The station can be mounted with the rear panel against the wall. If you want to
remove the insulation, a free space of about 20 cm must be left to the wall (see figure).
7.
For the operation of the hydraulics and a subsequent servicing, a free space of
at least 60 cm to the front (controller) and to both sides must be left (see figure).
8.
Remove the upper elements of the insulation at the connections of the modules.
Содержание SolexMega-Kaskade HZ
Страница 37: ...8 Spare parts specialist 2016 05 996098460 mub en V02 37 8 2 Spare parts hydraulics primary circuit ...
Страница 38: ...8 Spare parts specialist 38 996098460 mub en V02 2016 05 8 3 Spare parts hydraulics secondary circuit ...
Страница 39: ...8 Spare parts specialist 2016 05 996098460 mub en V02 39 8 4 Spare parts installation set ...