Installing the IpChannel Bank
33
SmartNode 4300 Series User Manual
3
• Hardware installation
Do not connect the power cables to the DC power source at this time
. For the DC power source, the IpChan-
nel Bank is equipped with a two-position, screw-down terminal block (see figure 13).
Grounding stud
- DC input
+ DC input
Figure 13. DC connector, -DC and +DC input view
1.
Connect the earth ground of the DC source to the grounding stud on the DACS as described in the previ-
ous section entitled “Grounding the Model SN4300—AC and DC units.”
2.
Strip back the insulation on each of the wires approximately 1/4-inch.
3.
Insert the stripped end of the positive lead into the
+DC input
of the terminal block. Tighten the screw
until the power lead is firmly fastened. Repeat the procedure for the negative lead, using the
-DC input
of
the terminal block. Make sure that all strands of the wire are captured and that there are no exposed wires.
4.
Repeat steps 1 through 3 to install the remaining DC power connection.
CAUTION
An approved power supply that incorporates a disconnect
device must be used and positioned within easy reach of the
operator’s position.
5.
Connect the equipment to a 36–72 VDC, 2.5A supply source that is electrically isolated from the AC
source. The 36–72 VDC source is to be reliably connected to earth ground.
6.
Verify that the green
POWER
LED is lit.
Hardware installation is complete. Refer to chapter 4,
“Getting Started with the SmartNode 4300 Series”
on
page 34.