2
Installation Procedure
Before installing the DSU/CSU, read the
Important Safety Instructions beginning on
page 25.
The following procedure is for experienced DSU/CSU users who are familiar with the
3160 DSU/CSU installation process and have no special requirements for their
application. See the
ACCULINK DSU/CSU Operator’s Guide for more information.
1. Attach the power cord to the rear of the DSU/CSU and the other end to a grounded
115 Vac power outlet.
2. Attach the DSU/CSU network connection to the T1 network using the appropriate
cable. Attach the 3160 DSU/CSU to the customer premises equipment via the DTE
(DSX-1) and/or port connectors.
3. Power on the DSU/CSU to perform the power-on self-test.
4. If you intend to use front panel emulation, connect the cable from the PC to the
COM port on the rear panel of the DSU/CSU.
5. If you intend to manage the DSU/CSU with SNMP over an Ethernet LAN, connect
the 10BaseT port to your LAN and assign an IP address to the port. See
Configuration Procedures on page 4.
6. If you do not intend to use the DTE Drop/Insert T1 port, disable it. See
Configuration Procedures on page 4. The default setting for this port is Enabled.
7. Customize the configuration options for your environment as required.
8. During the power-on self-test, the FAIL LED flashes, then all LEDs blink twice.
When the test is complete, verify that the DSU/CSU is functional by observing that
the OK, NETWORK SIG, and DTE SIG LEDs are lit.