Section
Chapter 3. Cabinet Installation
System Initialization
1. Confirm that the DBS power switch is
OFF.
2. Plug the power cord into a dedicated 120V 15 amp AC wall outlet.
Note: A surge protector should be installed on the power cord.
3. Set SW1 on the CPC card to RAMCLR (RAM Clear).
‘igure 3-17. CPC memory clear switch
4. Turn the power switch on.
As the system loads, the bottom LED lamp on the CPC card will flash.
.
5. Once the bottom LED lamp on the CPC card stops flashing, set SW on
the CPC to
DES-70-300
DBS Manual Issued
3-l 7
Содержание DBS 96
Страница 10: ...List of Tables Section 300 installation X DBS Manual Issued 8 l 95 DBS 70 300 ...
Страница 13: ...1 2 DES Manual Revised 4 3 96 DES 70 300 ...
Страница 19: ...DES Manual Issued 8 l 95 DES 70 300 ...
Страница 28: ...3 2 DBS Manual Issued 8 l 95 DES 70 300 ...
Страница 47: ...4 2 DBS Manual Issued 8 l 95 DBS 70 300 ...
Страница 91: ...5 2 DBS Manual Issued 8 l 95 DBS 70 300 ...
Страница 127: ...6 2 DBS Manual Issued 8 l 95 DBS 70 300 ...
Страница 139: ...7 2 DES Manual Issued 8 l 95 DBS 70 300 ...