How to fill it
Proceed as follows.
Step
Action
1
Remove the cover plate of the ice water reservoir.
2
Put the overflow pipe with stop in the appropriate opening in the ice water reservoir (right hand
corner)
3
Fill the reservoir with water until 1 cm under the overflow pipe.
4
Add the amount of 1, 2, 3 Benzotriazol needed to the ice water reservoir.
5
Put the cover plate back in place.
IB ice thickness sensors
OM/IB tanks 1200 liter and smaller are equipped with 1 sensor. The so 50% sensor. Factory setting
of this sensor is corresponding with an ice diameter of 76 mm (+/- 2mm)
All other OM/IB and RM/IB tanks are equipped with 2 sensors, a +50% (brown cable) and -50% (white
cable) one, for each cooling unit. When the -50% sensor is selected the ice is formed till a diameter of 53 mm
(+/- 2 mm)
The sensor must always be installed according to underneath drawing and may not be moved
How to use:
Factory settings: all IB systems equiped with a +50/-50% sensor and selector switch, the system is always set
at -50%
If the milk cooling is within its limits (depending on the performance class) it is strongly advised to work
with the -50% sensor, this is to avoid ice blocking. Generally this position can be used until a milk quantity
equal to +/- 75% of one milking, when the milk is not pre cooled with mains water. If the milk is pre cooled
this position can be used until a milk quantity equal to +/- 100% of one milking.
+50% (brown cable)