Connections
test
1. Check over all wiring and mounting and verify correct
installation. Especially check the 120/230 Vac connections,
the motor connections, and the grounding.
2. With the power Off, verify that the switch S1 settings are set
as follows. The 5345/5445 leaves the factory with these
settings.
These settings enable the mid-range instability control, enable
idle current reduction, set the step size to 1/25 step, and enable
microstep current boost.
WARNING
Make sure the 120/230 Vac power is removed before proceeding.
3. Unplug the J1 motor connector.
4. Switch On the 120/230 Vac power. Check that the POWER
LED is the only LED On.
5. Again switch the power Off.
6. Connect the J1 motor connector.
7. Switch On the 120/230 Vac power. Check that the POWER
LED is the only LED On. If the POWER LED is On, the
connections to the motor are OK.
1
2
3
4
5
6
ON
3 - 2
5345/5445 Installation and Hardware Manual
Rev F
Artisan Technology Group - Quality Instrumentation ... Guaranteed | (888) 88-SOURCE | www.artisantg.com