11
RECOMMENDATION
- Mains wires are brought into the junction boxes via prefabricated holes in the casing (1) and (2).
The holes are sized for fitting the strain relievers (3) and (4) supplied.
-
For the upper junction box with 3kW capacity, > 15A fuse/ > 2.5# wire should be used.
For lower junction boxes, an auth. electrician should calculate the correct fuse and wire.
Make sure that all wires are not trapped or pinched and free from damage.
3.7.5 Fitting instructions
3.7.6 Fitting recommendation
!
WARNING
!
The product should be filled with water before the power is switched on. Upper cylinder should
be filled first.
!
Fixed electrical fittings must be used for installation. Any electric fittings must be installed by an
authorised electrician. Components for disconnection must be included in the fixed electrical
installation in accordance with applicable standards and regulations.
!
Mains cable should withstand 90°C continuously. A strain reliever must be fitted.
!
CAUTION
!
The product must have a clearance for servicing of 40 cm in front of the cover / 10 cm over the
mixer valve.
!
In case of damage to the power supply cable, this should be replaced with custom cable from
an auth. electrician.
2
1
2
3.7.7 Strain relievers
Strain relievers (3) and (4) are supplied with the
product and mounted in prefabricated holes for
wires (1) and (2). All electrcal work should be per-
formed by an authorised electrician.
3
4