3. INSTALLATION
3.1. LOCATION
The site location should be precisely defined, indicating the levels of alignment and height of
the possible reference points, such as: roads, kerbs, milestones, fences, pavilions, pylons,
etc.
3.2. PLANNING
The coordination of the transport and the crane must be scheduled or, if this is not possible,
a tow-truck suitable for the weight of the
CMS-17
Switching and Breaking Substation
[1]
.
The existence of any circumstance or object that could impede or obstruct the smooth operation
of the installation must be indicated (posts, cables, ditches, walls, pipelines, etc.), marking their
positions on the drawing with the corresponding measurements.
Due to technical reasons concerning the protection and safety of people and property, the
conditions of the installation site and its design must be in accordance with the applicable
regulations on High Voltage.
Similarly, please take into account the assembly instructions provided by the Electric Utility,
which is aware of the regulations and also takes into account any particularities in the
electrical network to which the Switching and Breaking Substation is to be connected.
[1]
See sections
1.3 Mechanical Characteristics and 2.1.Lifting Methods
.