Page 12 of 20
11.08.2011
IG-178-GB
version 01
Page 12 of 24
GENERAL INSTRUCTIONS FOR
CMS-17
SWITCHING AND BREAKING SUBSTATION
CAUTION:
In the event that any anomaly is found, please contact
Ormazabal's
Technical-
Commercial Department immediately.
2.4. SEA TRANSPORT
The transportation should be carried out using "open top" or "flat-rack" containers.
To eliminate the risk of water intake, protect the front ventilation outlets located in the doors
with an elastic plastic band rolled around the perimeter several times.
Attach 2 planks of 1500 x 150 x 20 mm to support the
CMS-17
in the container.
Once positioned inside the container, attach a 100 x 100 x 10 mm and 100
mm long square
to each corner of the building. They must be welded to the floor of the container, in order to
avoid any movement during transportation. Lastly, place two slings transversally over the
enclosure, after having placed corner pieces below the slings in order to protect the
enclosure from possibly rubbing against the slings.
2.5. DELIVERY CONDITIONS
The
CMS-17
Switching and Breaking Substation is supplied fully assembled and ready for
connection to the MV supply.
Upon receipt of the
CMS-17
substation, carefully check the following:
That the characteristics of the different components that make up the electrical
equipment that are listed in the corresponding name plates coincide with the order.
The general condition of the assembly.
Figure 2.4: Sea transport of CMS-17