3.13.1 Electrical connection of hydraulic and coolant pump
The connection points of the external devices are located on
the side of the control cabinet.
hydraulic power pack (1)
Coolant pump (2)
3.14
First commissioning
Qualification of personnel on page 12
WARNING!
First commissioning may only take place after proper installation.
When the surface grinding machine is first put into operation by inexperienced
personnel or inexperienced users, you endanger people and equipment. We do not
accept any liability for damages caused by incorrectly performed commissioning.
ATTENTION!
Before commissioning the machine, all bolts, fastenings and protections must be
checked and retightened as necessary!
ATTENTION!
Before putting the machine into operation, the fill levels must first be checked.
Hydraulic power unit
Coolant
Central lubrication
Make sure that the slideway oil reaches the lubrication points.
3.14.1 Warming up the machine
ATTENTION!
If the surface grinding machine, in particular the grinding spindle, is immediately
operated under grinding load when it has cooled down, it may be damaged. A machine
that has cooled down, such as may occur immediately after transport, should therefore
be warmed up first for the first 20 minutes without grinding load.
2