Mounting instructions PYROLINE
®
Rapid fire protection duct
EN | 47
Mounting on a support system
6 2 2
Wall penetration in dry/lightweight construction wall
The mounting process described below allows achievement of a fire re-
sistance class I90, depending on the fire resistance length of the wall. For
I 120, see “6.3.8 Mounting a wall/ceiling penetration” on page 62.
Note!
The distance from the wall to the next suspension points must not exceed
350 mm.
BSKM 0407/ 0711/
1025
BSKM 0407/0711/
1025
I30
I60
I90
5-10 mm
≤ 350 mm
2
1
7
6
3
4
5
Fig 51:
Wall penetration through dry/lightweight construction wall
1
Ceiling
2
Dry construction wall with
heat insulation
3
Mineral wool insulation, mater-
ial class A 1, melting point
> 1,000 °C, e.g. OBO MIW
4
Gap between ducts: 5‒10 mm
5
Mineral fibre plate as support
profile
6
Sealing with filler
7
For BSKM 1025: insert lid
support BSKM-DS 1025
• Lay the ends of the duct on a mineral fibre plate
5
.
• When plugging the mineral wool
3
, it is advisable to use an im-
plement such as a stick and push as much as possible into the gap
above the ducts, in order to achieve as high a density as possible.
• Moisten the surface of the mineral wool and the mineral fibre plate
slightly with water and coat both sides with filler
6
with a thickness of
min. 2 mm.