Introduction 3
Practice 450-1011-201
(6)
Install the peripheral and external equipment according to the floor plan
and wiring logs.
(7)
When all connections have been made and verified, initialize the system
according to the instructions in the Guide to DNC Base Software
Installation, 450-1011-302. (That document is available to authorized
system installers.)
Getting Ready
Before unpacking and installing the equipment, you should ensure that you
have on hand the completed worksheets and forms from the Site Records,
450-1011-152. Also included in theSite Records are the hardcopy record of
the assigned shelf positions of the SRUs and a detailed floor plan for the site.
All connections and the equipment layout should conform to the worksheets in
the Site Records.
In addition, you should ensure that all the tools, equipment, and materials
required for installing the system are on hand. All the items required are listed
here for your convenience; the specific items required for any given
procedure are listed again at the beginning of the procedure.
TOOLS:
1
Chalk line
1
Truck dolly
1
Knife
1
Small wire cutter for plastic tie-wraps
1
Carpenter's level
1
Hexagonal nutdriver (1/4 inches)
1
Hexagonal nutdriver (3/8 inches)
1
Hexagonal nutdriver (3/16 inches)
1
Allen wrench (5/64 inches)
1
Small flat-blade screwdriver
1
Medium Phillips screwdriver
1
Wire-wrap tool