background image

19

GAS SUPPLY & PIPING

•  All gas piping must be installed in compliance with 

local codes and utility regulations. In the absence 
of local codes the gas line installation must comply 
with the latest edition of the National Fuel Gas Code 
ANSI Z223.1 or CAN/CGA B149 Installation Codes.

•  Some local codes require the installation of a manual 

main shut-off valve and ground joint union external 
to the furnace as shown in Figure 10. The shut-off 
valve should be readily accessible for service and/
or emergency use. Consult the local utility or gas 
supplier  for  additional  requirements  regarding 
placement of the manual main gas shut-off.

• 

The manifold pressure must be set to the appropriate 
value  for  your  installation.  Refer  to  the  Manifold 
Pressure  Adjustment  section  (page  22)  for 
adjustment instructions.

•  Gas piping must never run in or through air ducts, 

chimneys, gas vents, or elevator shafts.

•  Compounds used to seal joints on gas piping must 

be resistant to the actions of LP propane gas.

•  The main gas valve and main power disconnect to 

the furnace must be properly labeled by the installer 
in case emergency shutdown is required.

•  An 1/8 inch NPT plugged tap must be installed in 

the gas line immediately upstream of the gas supply 
connection to the furnace for use when measuring 
the gas supply pressure. The plug should be readily 
accessible for service use.

•  A drip leg should be installed in the vertical pipe 

run to the unit (Figure 10).

This unit only has right side gas entry. When connecting 
the gas, provide clearance between the gas supply line 
and the entry hole in the unit’s casing to avoid unwanted 
noise and/or damage to the unit. A typical gas service 
hookup is shown in Figure 10.

Table 13 (page 29) lists gas pipe capacities for standard 
pipe sizes as a function of length in typical applications 
based on nominal pressure drop in the line.

Leak Check

 WARNING:

FIRE OR EXPLOSION HAZARD

Never test for gas leaks with an open flame. Check 
all connections using a commercially available 
soap  solution.  A  fire  or  explosion  may  result 
causing  property  damage,  personal  injury  or 
loss of life. Failure to follow the safety warnings 
exactly could result in serious injury, death or 
property damage.

After the gas piping to the unit is complete, all connections 
must be tested for gas leaks. This includes pipe connections 
at the main gas valve, emergency shutoff valve and 

other gas connectors. A soap and water solution can be 
applied on each joint or union using a small paintbrush. 
If any bubbling is observed, the connection is not sealed 
adequately and must be retightened. Repeat the tightening 
and soap check process until bubbling ceases.

• 

If pressure testing the gas supply lines at pressures 
greater than 1/2 psig (14 inches WC), the unit must 
be disconnected from the gas supply piping system 
to prevent damage to the gas valve.

• 

If the test pressure is less than or equal to 1/2 psig 
(14 inches WC), the unit must be isolated from the 
gas supply line by closing the manual shut-off valve.

High Altitude Conversion

Conversion of this unit must be performed by qualified 
service personnel, using only approved parts. All 
installations must be made in accordance with the National 
Fuel Gas Code or with local jurisdiction codes.

If installing this unit above 2,000 feet, the input rate must 
be reduced 4% per 1,000 feet of altitude (Example: 12% 
at 3,000 feet, 16% at 4,000 feet, etc). 

NOTE: 

Deration is 

necessary to compensate for low atmospheric pressure 
at high altitudes.

 WARNING:

The reduction of input rating necessary for high 
altitude installation may only be accomplished 
with factory supplied orifices. Do not attempt to 
drill out orifices in the field. Improperly drilled 
orifices  may  cause  fire,  explosion,  carbon 
monoxide poisoning, personal injury or death.

High altitude conversion can be field performed by a 
simple adjustment of manifold pressure or a change of 
the orifices (if necessary) as described on page 22. The 
changes required depend on the installation altitude and 
the heating value of the gas (based on sea level) which 
can be obtained from your local gas utility.

Ground

Joint

Union

Dripleg

Shut-Off Valve

with 1/8 NPT

plugged tap

Burner

Assembly

Manifold

Some utilities

require Shut-Off

Valve to be

4 to 5 feet

above floor

Automatic Gas Valve

 (with manual shut-off)

Figure 10. Typical Gas Hookup - Right Side Entry

Содержание iHybrid DF6SF Series

Страница 1: ...ice personnel for this type of equipment After completing the installation return these instructions to the customer s package for future reference WARNING DO NOT DESTROY PLEASE READ CAREFULLY AND KEE...

Страница 2: ...ation 4 Emergency Heat 4 Defrost Operation 4 Operating the Heat Pump for Automatic Cooling and Heating 5 Oper the Indoor Blower Continuously 5 Shutting the Heat Pump Off 5 HEAT PUMP MAINTENANCE 5 Regu...

Страница 3: ...Start Checklist 20 Start up Procedure 20 Air Circulation 21 Short Cycle Protection 21 System Cooling 21 Secondary Heating 21 Verifying Adjusting Temperature Rise 21 Verifying Adjusting Firing Rate 21...

Страница 4: ...rmostat manufacturer s User Manual for detailed programming instructions Cooling Operation 1 Set the thermostat s system mode to COOL or AUTO and change the fan mode to AUTO See Figure 1 2 Setthetempe...

Страница 5: ...gure 1 NOTE The system will not operate regardless of the temperature selector setting HEAT PUMP MAINTENANCE CAUTION Shut off all electrical power to the unit before performing any maintenance on the...

Страница 6: ...ed shirt and appropriate breathing protection when working near this insulation If contact with skin occurs wash immediately with soap and water In case of contact with eyes flush immediately with wat...

Страница 7: ...designed to provide the correct flow rates and external pressure rise An improperlydesignedductsystemcanresultinnuisance shutdowns and comfort or noise issues Installationofequipmentmayrequirebrazingo...

Страница 8: ...deration should also be given to availability of electric power service access noise and shade A clearance of at least 36 inches from the blower access panel and from the louvered control access panel...

Страница 9: ...combustion the flame roll out control located above the burners will open turningoffthegassupplytotheburners Thissafetydevice is a manually reset switch IMPORTANT NOTE DO NOT install jumper wires acr...

Страница 10: ...NNEMENT AU MONOXYDE DE CARBONEd Le non respect des consignes suivantes portant sur chacun des appareils raccord s au syst me d vacuation mis en service pourrait entra ner l empoisennement au monoxyde...

Страница 11: ...leaks in the heat exchanger The cover for the opening shall be attached in a way that will prevent leaks If outside air is utilized as return air to the unit for ventilation or to improve indoor air...

Страница 12: ...C 25 50 or less Fiber duct work may be used in place of internal duct liners if the fiber duct work is in accordance with the current revision of the SMACNA construction standard on fibrous glass duct...

Страница 13: ...ge to the unit should be supplied from a dedicated branch circuit containing the correct fuse or circuit breaker for the unit Anelectricaldisconnectmustbelocatedwithinsight of and readily accessible t...

Страница 14: ...ntrance Recommended wire gauge and wire lengths for typical thermostat connections are listed in Table 4 Several thermostat options are available depending on the accessories installed with the unit S...

Страница 15: ...for heat anticipator settings Configuring the Variable Speed Blower The variable speed blower has been designed to give the installer maximum flexibility for optimizing system performance efficiency...

Страница 16: ...above the terminate set point or when the Y input is removed whichever occurs first NOTE If a demand curve is selected which has a 30 second compressor time delay in defrost the delay is reduced to 10...

Страница 17: ...nect the other end of the spare wire to R at the indoor unit or thermostat Thermostat Demand Wiring TheComfortAlertmodulerequiresatwostagethermostat to operate properly The Y2 thermostat wire entering...

Страница 18: ...ndicates a demand signal is received from the thermostat but current to the compressor is not detected by the module The TRIP LED typically indicates if the compressor protector is open or the compres...

Страница 19: ...ge personal injury or loss of life Failure to follow the safety warnings exactly could result in serious injury death or property damage After the gas piping to the unit is complete all connections mu...

Страница 20: ...rical disconnects to energize the system Air Circulation Leave the thermostat system mode on OFF and set the fan mode to ON Blower should run continuously Check the air delivery at the supply register...

Страница 21: ...failure 1 Placethermometersinthereturnandsupplyairstream asclosetotheunitaspossible Thethermometeronthe supplyairsidemustbeshieldedagainstdirectradiation from the heat exchanger to avoid false reading...

Страница 22: ...tem is installed according to these instructions no refrigerantchargingisrequired Ifrepairsmakeit necessaryforevacuationandcharging itshould only be done by qualified trained personnel thoroughly fami...

Страница 23: ...e energized opening the compressor contactor 5 If the thermostat does not satisfy on 2nd stage heat pump mode the thermostat or outdoor sensor will call for the back up gas heat NOTE If the unit is sw...

Страница 24: ...ilure the warm up is increased by 3 seconds on the next try If successful the timing remains fixed at this level In general whenever ignition failure occurs the warm up interval is increased by 3 seco...

Страница 25: ...ion in the gas supply piping at the unit 10 Remove the piping between the gas valve and the ground joint union if necessary 11 Remove the screws that secure the burner assembly in place and the burner...

Страница 26: ...e The circulating air blower and combustion blower will continue to operate if the over temperature limit control opens Troubleshooting If the unit does not operate in the cooling mode check the follo...

Страница 27: ...y Entry 15 75 23 75 29 75 2 9 1 8 4 0 12 45 12 45 4 0 D 8 75 Horizontal Supply Duct Opening Horizontal Return Duct Opening 4 0 1 75 9 75 24 75 16 0 Condensing Coil 13 5 16 0 16 0 C 13 5 figures tables...

Страница 28: ...t 5 6 7 46 800 72 000 65 000 100 000 78 000 120 000 0 0 550 63 732 73 700 59 1170 63 750 77 1255 71 1 0 650 53 865 62 800 60 1240 60 900 64 1395 64 0 1 750 46 998 53 1000 48 1640 45 1050 55 1720 52 1...

Страница 29: ...346 50 72 360 720 106 34 170 340 52 69 346 692 108 33 167 333 54 67 333 667 110 33 164 327 56 64 321 643 112 32 161 321 58 62 310 621 114 32 158 316 60 60 300 600 116 31 155 310 62 58 290 581 118 31 1...

Страница 30: ...entetavertirlacompagnie du gaz en utili sant le t l phone d un voisin A d faut de la compagnie du gaz avertir le service des pompiers C Enfoncer ou faire tourner le robinet gaz la main seulement Nejam...

Страница 31: ...suitable on systems that exceed 150V to ground 4 If any of the original wire as supplied with the furnace must be replaced it must be replaced with wiring material having a temp rating of at least 105...

Страница 32: ...t wires from the blower remain connected to the board thermostat terminals after making the field thermostat connections 7 Wiring shown for single stage operation For two stage operation move brown wi...

Страница 33: ...Flashes 230 VAC Neutral Reversed or No Ground 5 Flashes False Flame or Gas Relay Shorted Continuous Flash f f O f f O r e w o P W O L L E Y T H G I L S U T A T S N O I T I D N O C T L U A F Low Flame...

Страница 34: ...re that wires from the blower remain connected to the board thermostat terminals after making the field thermostat connections 7 Wiring shown for single stage operation For two stage operation move br...

Страница 35: ...hart Cooling Remove refrigerant when above curve Add refrigerant when below curve Figure 17 Charging Chart for 2 Ton Units 200 220 240 260 280 300 320 340 360 380 400 420 440 460 480 500 520 540 560 5...

Страница 36: ...hart Cooling Remove refrigerant when above curve Add refrigerant when below curve Figure 19 Charging Chart for 4 Ton Units 200 220 240 260 280 300 320 340 360 380 400 420 440 460 480 500 520 540 560 5...

Страница 37: ...heck for excessively low thermostat setting Check evaporator airflow coil blockages or return airfilter Check ductwork or registers for blockage Faulty metering device Check TXV bulb installation size...

Страница 38: ...mpressor protector reset time due to extreme ambient temperature Compressor windings are damaged Check compressor motor winding resistance ALERT Flash Code 6 Yellow LED Open Start Circuit Current only...

Страница 39: ...ompressor short cycling Verify Y terminal is connected to 24VAC at contactor coil Verify voltage at contactor coil falls below 0 5VAC when off ALERT Flash Code 5 6 or 7 displayed incorrectly Open Circ...

Страница 40: ...lateur qualifi un organisme de service ou le fournisseur de gazstaller service agency or the gas supplier Ne pas entreposer ni utiliser de l essence ni d autres vapeurs ou liquides inflammables dans l...

Страница 41: ...41...

Страница 42: ...42...

Страница 43: ...43...

Страница 44: ...________________________________________ UNIT SERIAL ________________________________________ UnitInstalledMinimumclearancesper Figure 2 page 8 YES NO INSTALLER NAME CITY________________________ STATE...

Отзывы: