General

The installation must only be carried out by competent
personnel.

The enclosed materials are those required for the install-
ations described (see page 17). In special cases, they may
need to be supplemented. If unsure, contact the supplier.
Information regarding applicable standards and regula-
tions must be obtained prior to the installation and
commissioning of the solar panel system. The electrical
installation, and notification to the power supplier, must
be carried out by qualified electricians. The form concern-
ing the inverter must be enclosed with the notification.
(Pre-completed form is available on www.nibe.se) Please
note that the installation must not be put into use before
the power supplier has given its approval.

NOTE

Installation of a solar panel is an extensive inter-
vention on an existing roof. The roof covering,
particularly on converted and inhabited loft
spaces or where the roof's minimum angle is
undersized (relative to the covering), may re-
quire further measures against moisture because
of wind pressure and drifting snow, this must
be evaluated by the installer on a case to case
basis. The roof design must be able to handle
the wind and snow loading that can occur in
the region.

Static load

The installation may only be carried out on roof surfaces
or support constructions with sufficient carrying capacity
and strength. The static load capacity of the roof and
roof construction must if necessary be examined before
the solar panels are installed. Great importance should
be placed on the condition of wood roof structures and
the potential of screwing the mounting devices for the
solar panels to the structure. The roof construction must
be reinforced if necessary. Inspection of the whole solar
panel installation in accordance with DIN 1055 part 4
and 5, or in accordance with country specific regulations
is required, in particular, in areas with snow fall and
strong winds. The characteristics of the installation's
location (prevailing wind direction, whirl winds etc.) must
also be included in the calculation/evaluation of
whether these could mean increased loads. The solar
panels must be installed so that snow drifts from snow
guards or caused by special conditions in the installation
location cannot occur in the vicinity of the solar panels.

The distance from the outer edge of the roof must be at
least 1 m at the sides of roofs and 0.2 m at ridges and
eaves, this is to reduce the risk of the wind ripping the
solar panels off.

The installation system according to DIN 1055 part 5 for
snow zone II is intended for use up to 400 m above sea
level. If the installation is made on a tiled roof, it is recom-
mended that the snow is cleared if it reaches a depth of
more than 30 cm on the solar panels (NOTE! If the snow
has melted, been packed down and then more snow
has fallen and so the density has increased, the snow
may need to be cleared - even though it is not 30 cm
deep.)

If there is a risk that the snow will slide down onto the
panels and in particular behind the rear of raised panels,
snow guards must be installed to prevent this.

Ensure that the material under roofs with roof tiles is
sufficiently stable to support the roof mounting points.
Otherwise the roof must be reinforced. The installer must
evaluate this and make a decision, if uncertain a structur-
al engineer should be consulted. We recommend that
the roof tiles are cut down so that there are no point
loads between the roof and the roof brackets. The min-
imum distance between roof tiles at overlap points and
the underside of the brackets is 3 mm, this is in order to
allow for any movements in the mounting system in re-
action to the loads that occur.

Lightning protection

If external lightning protection is installed, the solar
panels and the roof structure must be integrated so that
the solar panel field is protected from a direct lightning
strike. The combined solar panel area must be located
within the protective area provided by the lightning
protection. A safety distance of 0.5 m in all directions
from the solar panels to the periphery of the protected
area must be observed.

Safety instructions

Applicable safety regulations for working on roofs and
similar constructions must be followed.

Barriers to protect against falling parts must be in-
stalled. This is particularly important for high buildings
and locations where a lot of people pass below the
roof/under the building.

Personal safety equipment or scaffolding must be used
when working on roofs, according to the applic-
able.regulations.

Adequate measures must be taken during the install-
ation so that the solar panel does not come loose and
fall.

Observe the safety distance to the current conducting
cables.

7

Chapter 3 |

Installation

PV Solar package

3 Installation

Содержание PV 3031

Страница 1: ...Installer manual PV Solar package Accessories IHB GB 1648 3 331737...

Страница 2: ......

Страница 3: ...ponents 7 3 Installation 7 General 8 Installation and positioning 9 4 Mounting 9 15 5 Electrical connection 15 Outline diagram 18 6 Commissioning and programming 18 Guided first commissioning 18 Count...

Страница 4: ...ilitate using the product Marking The CE marking means that NIBE ensures that the product meets all regulations that are placed on it based on relevant EU directives The CE mark is obligatory for most...

Страница 5: ...2 x Roof mountings for tiled roofs sheet metal roofs seamed sheet metal roofs or felt roofs excl mounting screws 36 x 22 x 12 x Al rails 2 1 metre 48 x 32 x 16 x Mountings for solar panels end clamps...

Страница 6: ...cket felt roof Roof bracket tiled roof Roof bracket sheet metal roofs Roof bracket seamed sheet metal roofs LEK Centre clamp Mounting rail L profile Joint profile LEK End clamp PV Solar package Chapte...

Страница 7: ...r panels The distance from the outer edge of the roof must be at least 1 m at the sides of roofs and 0 2 m at ridges and eaves this is to reduce the risk of the wind ripping the solar panels off The i...

Страница 8: ...solar panels are located 100 is the insolation at a horizontal surface which in southern Sweden is between 900 and 1050 kWh m year The angle of inclined surfaces is 45 1 Calculate the annual solar rad...

Страница 9: ...mp System overview installation components 1 2 3 4 5 5 6 19 mm Roof bracket location 1 4 5 5 2 3 6 24 mm Before installing solar panels 1 Number of rows of installed solar panels x height of solar pan...

Страница 10: ...s are located in the upper groove NOTE The distance to the edge X must be the same on both sides Installing the roof brackets in tongue and groove Secure each roof bracket with 6 x stainless steel con...

Страница 11: ...screwed in to install a seal against the roof sheet A bitumen based roof and building sealant can be used re quired for textured sanded surfaces 3 Install the L profile adjust the height to the other...

Страница 12: ...nting rails are secured in the roof brackets with T bolts and locking nuts 8 mm Caution Check that the head of the T bolt is vertical in the mounting rail after tightening The rectangular hole in the...

Страница 13: ...anel Slide the centre clamp towards the solar panel and connect 5 Position the second solar panel on the mounting rail and move the solar panel towards the centre clamp Connect the cable to the previo...

Страница 14: ...Install the following rows in the same way PV Solar package Chapter 4 Mounting 14...

Страница 15: ...e 4 mm up to 100 m in length not supplied Alternatively 3 kW All panels are connected in series Alternatively 6 kW All panels are connected in series Alternatively 9 kW The panels are connected in two...

Страница 16: ...these can be run underneath the roof tiles or ceiling To prevent moisture penetrating under the roof tiles or through the damp barrier at the holes for the electrical cables diffusion sealed lead ins...

Страница 17: ...re installed connectors 14 m is supplied and can be used for roof installation Grounding solar panels Solar panels must be earthed in the inverter or an extern al junction box Lightning protection For...

Страница 18: ...inverter is installed The inverter then downloads the mains network paramet ers that apply for that country see the Installation manual and directions for use for the relevant inverter for more inform...

Страница 19: ...a language 2 Short press confirm selected language 3 Press back up the menu tree Esc 1 Press Date format is marked 2 Short press confirm selection Set date 1 Press to select a date format e g day mon...

Страница 20: ...h 6 Press the minutes are changed 7 Short press the selected minute is saved 8 Press back up the menu tree Esc 1 Press Country code sel is marked 2 Short press confirm selection Set country NOTE The c...

Страница 21: ...the glass reverse and aluminium frame are undamaged Check that all electrical wiring and connections are intact and not coated with anything Mechanical cleaning is not usually required and is not reco...

Страница 22: ...re class 1638x982x40 mm External dimensions LxWxH Anodised silver Version with aluminium frame 19 kg Weight solar panel 2x1000 mm Connection cables with pre installed con nectors Inverter 847x400x225...

Страница 23: ...ter L Lightning protection potential compensation 7 M Marking 4 S Safety information Marking 4 Symbols 4 Safety instructions 7 Static load 7 Symbols 4 23 Chapter 9 Item register PV Solar package 9 Ite...

Страница 24: ......

Страница 25: ......

Страница 26: ......

Страница 27: ...ustrielle RD 28 Rue du Pou du Ciel 01600 Reyrieux Tel 04 74 00 92 92 E mail info nibe fr www nibe fr FR NIBE Energy Systems Ltd 3C Broom Business Park Bridge Way S419QG Chesterfield Tel 44 0 845 095 1...

Страница 28: ...WS name Gemensamt WS version a313 working edition Publish date 2017 02 03 08 06 NIBE AB Sweden Hannabadsv gen 5 Box 14 SE 285 21 Markaryd info nibe se www nibe eu 331737...

Отзывы: