16
NIBE
TM
AP-BW30
We reserve the right to make technical changes
83053706dUK – Translation of the operating manual
Connection of patch cable and LIN bus cable to the
regulator (via the strain relief):
1 Patch cable to the network link
2 LIN bus to the regulator board in the unit
3 Patch cable to the regulator
board in the unit
If the work on the heat pump regulator has been
completed, the cover can be clipped onto the wall
bracket.
+
=
NOTE.
A connection to a computer or a network can
be installed via the left bushing on the bottom
of the control element, thus allowing the heating
and heat pump regulator to be controlled
remotely. This requires that a shielded network
cable was laid up to the heat pump regulator
during the electrical connection work.
Operating manual for the heating and heat pump
regulator, version “Qualified heating engineers”,
“Web server” section.
NOTE.
The network cable can be exchanged at any
time. In order to be able to connect it, the
screen must first be removed.
Flushing and filling the unit
ATTENTION
The system must be absolutely free from air
before commissioning.
Installation of the control
element
NOTE.
Note the distance between the control element
and the unit.
For further details, see “installation plan”
Control element for wall-mounting
Fasten the wall bracket using the assembly materials
included in the scope of delivery.
There are 4 fixing hooks on the back of the control
element.
Hang the control element on the wall bracket using
the 4 fixing hooks and push down until it latches in-
to position.
1 Shielded terminal for LIN bus cable/strain relief
2 Strain relief