Assembly Instruction
1610 Royal Street
Jasper, Indiana 47546
Telephone 800.482.1717
Fax 812.482.8800
www.NationalOfficeFurniture.com
3248959
Rev, B
LOCHLYN
FREESTANDING FRAME
BUILD
6
12
With all frame sections installed, carefully stand the frame assembly upright
onto its glides
(Figure N).
FIGURE N
14
Position frame unit in final installation location and level the unit with the glides
by extending them no further than their midpoint.
CAUTION:
Do not
extend glides beyond 13mm (0.5in) from the glide
’
s fully
retracted position. Extending glides more than 13mm (0.5 in) can make the shelving unit
unstable.
If installing a
one (1) or two (2)
tier unit, this completes installation of the frame. If
installing a
three (3) through six (6)
tier unit, continue to Anchoring Requirements.
All
frame units from three (3) tiers through six (6) tiers are
required
to be permanently anchored
to the floor (see Floor Anchoring
Method pgs. 7
-
8; steps F1
-
F7) or wall (see Wall Anchoring Method
pgs. 9
-
12; steps W1
-
W9), regardless of configuration, usage, or if
multiple units are ganged together.
13
Install plastic caps from hardware bag
on the top of each vertical section
(Figure O).
FIGURE O