Step 36
The last Drive Pipe [3] requires (2) Pinion Gears on the Pipe. Slide the Drive Pipe into the Bronze Bushing in
last (2) Guide Plates [13], there will be one Pinion Gear lined up with each Pivoting Connector. Slide the
opposite end onto the swedged end of the previous pipe. If needed slide one of the Pinion Gears past the
joint in the pipes to align with the Pivoting Connector. Align the pre-drilled holes and secure pipes together
using Bolt [D] and Nut [G].
See Figure 34.
Cut excess Drive Pipe 3" past the last Pinion Gear.
Bolt [D]
Last Drive Pipe [3] with Pinion Gears
Nut [G]
Drive Pipe [3]
Figure 35
Step 37
Slide the Straight Coupling [17] over the end of the pipe near the Actuator and secure in place using (2)
Bolts [D] and Nuts [G].
See Figure 35.
Bolt [D]
Nut [G]
Drive Pipe [3]
Drive Pipe [3]