Maintenance
The
MultiCam
Plasma System will provide years of productive service if it is maintained properly. There are
daily, weekly, monthly, quarterly, and yearly maintenance steps required for each machine based on a 40-hour
work week.
MultiCam
recommends that any plasma system used in excess of 40 hours a week should have the
maintenance schedule adjusted accordingly. Each auxiliary system has specific maintenance procedures that must
be addressed in addition to the following maintenance procedures for the CNC machine.
Daily
The following tasks should be completed at the beginning of shift daily on the
MultiCam
Plasma System:
•
Wipe down rails
•
Check coolant level
•
Inspect the consumables – lube as required
•
Clean the cap and shield
•
Check the gas volume and pressure
Weekly
The following tasks should be completed at the end of shift weekly on the
MultiCam
Plasma System
•
Complete all daily tasks
•
Clean the machine thoroughly and remove any excess grease grime
•
Inspect the slag trays
•
Check the slat condition
•
Inspect the E-chain
•
Lube the torch O-rings
•
Rinse out the retaining cap and shield with distilled water
Monthly
The following tasks should be completed at the end of last shift monthly on the
MultiCam
Plasma System:
•
Complete all weekly tasks
•
Grease all the linear bearing cars
•
Inspect the Ohmic Sensor wiring
•
Check the motor engagement
•
Inspect the air filter
•
Clean out the controller plasma unit E-chain
Quarterly
The following tasks should be completed at the end of last shift quarterly on the
MultiCam
Plasma System:
•
Complete all monthly tasks
•
Inspect and clean the ground connections
•
Inspect the pump in-line filter
•
Change the swirl ring