4
WIRING BULBS CONTINUED:
With the Flash Unit in front of you ( back of
control box facing you )
See fig. 3
Start
attaching bulb wires to ceramic blocks in
groups of 3 (9 bulb units) or 4 (12 bulb units)
Insulation on the bulb wires is striped back
about
½
inch and they are ready to install.
The first group of bulbs nearest to the
control box are
Zone 1.
Locate this group of
wires from the left side and hook them to the
ceramic block for
Zone 1
by inserting them
under the tab and tightening screw at
position #1 (left terminal). Hook up wires
from the right side to position # 2 (right
terminal) of the same block
See fig. 4
The next group of bulbs (center of unit) will
use 2 ceramic blocks, these are
Zone 2
. The
bulb wires from the left side will hook up to
the ceramic block on the left position # 2 and
the wires from the right side will hook up to
the ceramic block on the right position # 1
The remaining group of bulbs (furthest from
control box) are
Zone 3.
These will hook up
to the remaining ceramic block. Wires from
the left side will go to position # 1 and wires
from the right side will go to position # 2
FIG. 3
Zone 1 Block
Zone 3
Block
Zone 2
Blocks
Sensor
Cutout
FIG. 4
IMPORTANT: Make sure all connections are tight before
installing cover!