8 Commissioning
VST_GA1_1.4 | Version 1.4 | 02/2022
14
8
Commissioning
Commissioning work may only be performed by qualified staff (see Chapter 2.2). The unit may
only be commissioned if the condition of the complete system complies with the applicable
guidelines and regulations.
INFORMATION
MRS recommends a functional test on site.
j
WARNING!
SUDDEN MOVEMENTS OF COMPLETE SYSTEM OR OF COMPONENTS
Danger due to unprotected moving components.
Before commissioning the system, please make sure that the complete system and all
parts of the system are in a safe state.
If necessary, secure all hazard areas with barrier tapes.
The operator must ensure that
the correct software has been embedded and corresponds with the circuitry and parameter
setting of the hardware (only for gateways supplied by MRS without software).
no persons are present in the vicinity of the complete system.
the complete system is in a safe state.
Commissioning is performed in a safe environment (horizontal and solid ground, no
weather impact)