Page 6
HW-Series Gas Fireplace
Part No. XG0190 - 071409
Installation
Installing Terminations with Built-In Frames
Installing Terminations with MSR Frames
1. Frame the termination opening to 12" x 12".
2. Fasten the termination to the studs using a minimum of 4 screws.
1. Frame the termination opening to 11" x 11".
2. Fasten the termination to the studs using a minimum of 4
screws.
Installing Terminations with MOSR Frames
MOSR
1. Frame the termination opening to 12" x 12".
2. Fasten the MOSR frame to the interior side of the studs using a
minimum of 4 screws.
3. Insert the termination into the MOSR frame as shown here, and
attach by screwing through the four pilot holes in the termination.
MSR
MTO-3 (4"/7")
PTO-3 (5"/8")
MTO-3F (4"/7")
PTO-3F (5"/8")
MTO-3 (4"/7")
PTO-3 (5"/8")
MTKOG
(4"/7")
PTKOG
(5"/8")
1. Ensure that the two
long
mounting brackets are facing the bottom
of the termination. (See inset). This will provide more heat protection
at the top of the termination, where temperatures are highest.
2. Attach to the faceplate of the termination using four sheet metal
screws.
Installing Heat Guards over Terminations
Installing The Standoffs
To avoid elevated mantel temperatures, all HW38DF gas
fireplaces are required to have the supplied standoffs installed.
The fireplace is supplied with two standoffs. Bend and install these
standoffs on top of the fireplace ensuring that the height of the standoff
maintains a 6.5" clearance.
Figure 6b.
Installing the standoff's.
Installing the Nailing Flange
Extension, or Non-Combustible
material
The Nailing Flange Extension is supplied with all Montigo Flush face
gas fireplaces. This Extension is required, unless Non-combustible
materials are used in its place, (see Figure 25).
Once the fireplace is moved into the framed opening, the supplied
nailing extension, or Non-combustible material must be placed along
the top edge of the fireplace. This can be nailed or screwed in place
to the framing, as illustrated below.
Figure 5a.
Installing a MTO / PTO termination.
Figure 5b.
Installing a MTO / PTO termination with the MSR frame.
Figure 5c.
Installing a MTO / PTO termination with the MOSR frame.
12
12
12
Figure 5d.
Installing a PTO termination heat guard.
11
11
12
12
Figure 6c.
Installing the Nailing Flange Extension, or Non-combusti-
ble materials above fireplace.