Infrastructure Requirements and Layout Planning
Dual Band EnCOVER VE™ Instant Coverage Solution User Manual
16
3.4.4
Installation Plan Example
The Following figure shows a floor plan map with all required marks:
Figure 10. Floor Plan Example
Notes:
•
The red VAP coverage circles are approximately 45, 58 and 67 foot (14, 18 and 21 m) radius
for the small, medium and large circles respectively (drawn according to the guidelines for
UMTS service, given in section
3.3.1).
•
VAP 3 is surrounded by dense objects, the bathroom and stairwell which would reduce
coverage in that area by the other VAPs.
•
VAP 5 is an example of a unit that provides good coverage down the hallways.
•
VAPs 11 and 13 are placed closer to the offices to cover them well but on the open side will
actually cover a much greater area which is why the coverage is larger and shown here
more as an oval than a circle.
•
The area between VAPs 7 and 14 outside the bathrooms would probably be the lowest
coverage spot in the building because of the bathrooms and stairwell on either side of that
area. If after the system installed, this area is still a little low on coverage, a VAP can be
added, but it may also be covered by VAP 14.
Note: The plan can be modified at any time by moving the units around or by adding units.